FOR PUBLICATION
ATTORNEY FOR APPELLANTS: ATTORNEYS FOR APPELLEE:
MICHAEL L. CARMIN VICKIE RENFROW
Andrews, Harrell, Mann, Carmin & Parker, P.C. Bloomington, Indiana
Bloomington, Indiana
LINDA RUNKLE
Bloomington, Indiana
IN THE
COURT OF APPEALS OF INDIANA
NANCY SALMON, et. al., )
)
Appellants, )
)
vs. ) No. 53A01-0107-CV-256
)
CITY OF BLOOMINGTON, )
)
Appellee. )
APPEAL FROM THE MONROE CIRCUIT COURT
The Honorable J. David Holt, Special Judge
Cause No. 53C02-0001-CP-132
January 11, 2002
OPINION - FOR PUBLICATION
BARNES, Judge
Appellants Appendix pp. 63-64. There was some argument made at the time
the annexation was proposed that its effective date be postponed until January 1,
1997, to allow the Residents more time to consider its potential impact, but
the City Council voted not to delay the effective date. There is
no record that a remonstrance was filed against the annexation.
At the City Council meetings where the Browncliff annexation ordinance was debated, Rule
13 of the Citys Utility Service Board (USB) was mentioned and discussed.
USB Rule 13, which applies to predominantly residential additions other than apartment developments,
provides that before the City will extend sewer service to a neighborhood, several
steps must be followed. Appellants Appendix p. 87. First, sixty percent
of the neighborhood residents must sign a petition expressing interest in receiving city
sewer service; this does not obligate the signatories to obtain sewer service.
After receiving a petition, the USB prepares the required engineering plans and obtains
construction cost estimates. After receiving those estimates, the USB notifies the residents
of the estimated cost per resident of constructing the sewer. At that
point, sixty percent of the residents must commit to hooking on to the
new sewer and pay a deposit before construction will begin. The Rules
and Regulations of the USB were attached to the annexation fiscal plan as
an exhibit.
On November 13, 1997, the Residents submitted a petition to USB indicating that
owners of sixty-nine of the eighty-four Browncliff properties were interested in possibly receiving
City sewer service. At that time, USB officials indicated that the cost
of extending the sewer would likely exceed the initial cost estimate mentioned in
the fiscal plan, and it was agreed that the City would pay for
a detailed engineering design plan for the sewer and would conduct rock borings
in the Browncliff Subdivision to arrive at a more precise cost estimate for
the project.
The City hired a consultant, at a cost of $37,250, to estimate the
cost of the project. Rock borings were also conducted, at a cost
of $5,000, although some Browncliff residents, including parties to the disannexation petition, did
not agree to allow borings to be conducted on their property. Sometime
after the consulting work was completed, the Residents were invited to an October
1, 1998, meeting to discuss the results. The City disclosed at this
meeting that the estimated cost of constructing a gravity sewer was $7,700 per
resident, and that the design followed the lay of the land and would
require the acquisition of easements through private property. It also reminded the
Residents that a good faith deposit would be required from sixty percent of
the property owners before any sewer construction would begin.
See footnote However, the City
agreed to investigate a low-pressure pump sewer system for the Browncliff Subdivision, which
the City indicated would not require the acquisition of easements because it would
follow the street right-of-ways, and additionally might result in a lower construction cost.
Thus, the Residents were asked not to commit to the gravity sewer
design at that time.
The City expended an additional $27,927 for a consultant to obtain cost estimates
for a low-pressure pump system. In early 1999, the City also began
exploring its ability to obtain the forty-six easements from Browncliff property owners that
would be necessary for the gravity sewer design; after six months of effort,
only nine property owners had agreed to grant easements. The City conducted
another meeting on March 25, 1999. At that meeting, the results of
the low-pressure sewer design consultation were communicated to the owners of forty-four Browncliff
properties. The City received only eighteen responses to a questionnaire handed out
at that meeting asking which sewer design option they preferred. On June
24, 1999, City officials met with William Kroll, president of the local neighborhood
association, and it was decided that the City would seek bids on both
the gravity and low-pressure sewer designs, and the Residents could decide which option
to pursue, if any, after receiving the results of the bids.
The City received three responsive and responsible construction bids on September 27, 1999,
the lowest of which resulted in a per household construction cost of between
$8,900 and $9,000.See footnote This was communicated to Kroll, and additionally the
City obtained an agreement from the low bidder to extend the sixty-day statutory
period for keeping a bid open by ninety days, or until February 27,
2000. Additionally, the City obtained a construction permit from the Indiana Department
of Environmental Management and sought approval for up-front funding for the project from
the USB in the amount of $665,000. The Residents, however, did not
choose a sewer construction design, but instead filed suit on January 26, 2000,
seeking to disannex their properties from the City because of its failure to
complete the sewer extension within three years of the annexations effective date, or
by February 10, 1999. The City moved for summary judgment, which was
granted on June 12, 2001. This appeal now follows.
(2) That the municipality has not provided police protection, fire protection, sanitary sewers, and
water for human consumption within the specific time limit for implementation, unless one
(1) of these services is being provided by a separate taxing district or
by a privately owned public utility.
(3) That the annexed territory is not receiving governmental and proprietary services substantially equivalent
in standard and scope to the services provided by the municipality, regardless of
topography, patterns of land use, and population density similar to the annexed territory.
The Residents claim they are entitled to relief under subsections (1) and (2),
but make no argument under subsection (3). We address the Residents two
arguments.
The Residents first argue that the City breached the annexation fiscal plan without
justification because it did not provide hookups to the sewer main within three
years of the annexation effective date, in violation of Indiana Code Section 36-4-3-16(b)(1).
The Citys first response to this argument is that it has fully
complied with the fiscal plan by virtue of its compliance with municipal policy
regarding sewer construction, as embodied in USB Rule 13. If the Citys
fiscal plan had explicitly stated that sewer hook-ups would be made available in
accordance with USB Rule 13, i.e. only after a petition had been submitted
by sixty percent of the residents, etc., there clearly would not have been
a breach of the fiscal plan in this instance. That was not
the case, however. The fiscal plan here could have been more clearly
written. The plan suggests in some places that sewer hook-ups would be made
available to the Residents regardless of compliance with USB Rule 13. It
states that the City
will ensure that sewer mains are available for hookup
to the Annexation Areas properties. Appellants Appendix p. 63 (emphasis added).
Additionally, section 8.01 of the fiscal plan, Sanitary Sewer Service, never references Rule
13. We cannot say there has not been a breach of the
fiscal plan, to the extent it suggests in places that the installation of
sewer hook-ups was to be entirely self-executed by the City within three years
of annexation.
However, under the plain language of the disannexation statute, a plaintiff seeking disannexation
or other relief must not only prove that the fiscal plan was breached,
but also that such breach was without justification. Justification is defined as
[a] lawful or sufficient reason for ones acts or omissions or [a] showing,
in court, of a sufficient reason why a defendant did what the plaintiff
. . . charges the defendant to answer for. Blacks Law Dictionary
870 (7th ed. 1999). Here, we find no material issue of
fact with respect to whether the City acted without justification in failing to
provide sewer main hookups within three years of the annexations effective date; it
is clear the City did have justification or a plainly sufficient reason for
not having provided sewer main hookups to the Residents within three years of
the Browncliff annexation.
Although not explicitly mentioned in the fiscal plan, USB Rule 13 was discussed
at City Council meetings where the Browncliff annexation was considered and its provisions
were explained to the Residents in attendance at those meetings. The Residents
were on notice as to its provisions and that the City intended to
follow them. Furthermore, the fiscal plan clearly provided that the City would
not pay the cost of constructing a sewer extension and that the cost
would be borne by the Residents. When the Residents filed the requisite
sixty percent interest petition in accordance with USB Rule 13 approximately twenty-one months
after the annexations effective date, the City initiated efforts to design and receive
cost estimates for the extension of sewer service to the Browncliff Subdivision.
The City also communicated the information it obtained to the Residents through group
meetings or through the neighborhood representative, Kroll. The City attempted to address
concerns of the Residents regarding costs and the granting of easements by investigating
alternative sewer designs, and by offering alternative payment plans for construction. The
City asked the Residents to choose which sewer design they preferred, but no
choice was made.
These facts establish the prima facie existence of justification for the Citys failure
to provide sewer main hookups within three years of the annexation date, thus
negating a necessary element of Residents cause of action that the City
acted without justification. Rather, the City followed the procedures for extending sewer
service provided in USB Rule 13 and varied from that rule in an
attempt to accommodate the Residents wishes and concerns. It expended considerable expense
and time in developing engineering plans and obtaining cost estimates. Before proceeding
to construction of the sewer, the City had good cause to insist on
some assurance from the Residents that the construction would be paid for.
In fact, it would be unreasonable and a waste of government resources for
a municipality to press forward with a large capital improvement project such as
this, the cost of which is to be entirely paid for by the
benefiting property owners according to established municipal policy, without first obtaining some assurances
that a large percentage of those property owners were actually willing to pay
for the project.
In the face of the Citys designated evidence, Residents were required to designate
evidence that would create a material issue of fact as to justification so
as to avoid summary judgment. They failed to do so. The
only piece of evidence that requires some discussion comes from the deposition of
Mike Phillips, the Citys Director of Utilities. Phillips acknowledged that some sewer
extension projects are not initiated by a neighborhood petition as provided in USB
Rule 13, but the Citys HAND Department.
See footnote The Residents essentially claim this
creates a question of fact as to whether the Browncliff Subdivision, as an
annexed territory, is treated unfavorably as compared to other parts of the City,
and that the City should have constructed the sewer extension without regard to
USB Rule 13. We disagree. Phillips also indicated that the HAND-initiated
projects were ones that would be financed in part by community development grants
intended to assist low-to-moderate income families and, therefore, that only part of the
cost of constructing the sewer extension would be recouped from the users.
The Residents have not pointed to any sewer construction projects that were City-initiated
outside of these special redevelopment projects and there is no reason to believe
that USB Rule 13 is anything but uniformly applied otherwise. The fact
that the City may choose to initiate sewer projects on certain occasions in
the absence of a sixty percent neighborhood commitment does not render its reliance
on USB Rule 13 unfair or unreasonable in other cases, particularly where it
is expected that the cost of the project will be fully funded by
the benefiting residents and not by special government grants.
As for the cost of providing sewer main hookups to the Residents, it
is true that the cost estimates for doing so greatly exceed the $3,000
estimate mentioned in the fiscal plan. This does not constitute a breach
of the fiscal plan. Indiana Code Section 36-4-3-13(d)(1) and (2) states that
a fiscal plan must indicate the estimated cost of planned services
to be
furnished to the territory to be annexed and the method or methods of
financing the planned services. (Emphasis added.) Here, the fiscal plan plainly
provided that the cost of constructing the necessary extension of the sewer main
would be borne by the Residents. The City essentially agreed to handle
the administrative, logistical, and engineering aspects of arranging for the sewer main extension,
but it did not agree to furnish a service to the extent of
paying for the construction itself. This process is in accordance with USB
Rule 13, which applies throughout Bloomington and states that neighborhood residents who wish
to have sanitary sewer service must pay the necessary construction costs to extend
the main, unless the construction cost is less than three times the estimated
annual sewer revenue from the potential customers, which was not anticipated to be
the case with the Browncliff Subdivision. Additionally, Indiana Code Section 36-9-23-29 permits
a municipality to charge a fee for connections to a sewer based on
the pro rata cost of constructing a local or lateral sewer sufficient to
serve the property. See Town Council of New Harmony v. Parker, 726
N.E.2d 1217, 1226 (Ind. 2000). We do not view the cost estimate
as an integral part of the annexation fiscal plan, because the City never
guaranteed that the cost would not exceed a certain level, or that it
would pay a portion of the construction cost, and the Residents were not
required to pay for an extension of sewer service as an obligation that
would attach after annexation. They were free to reject paying for the
sewer extension if they found it to be too expensive, as long as
the existing septic systems did not fail. Hence, there is no breach
of the fiscal plan based upon the Citys failure to obtain a construction
bid that was close to the cost estimate reflected in the fiscal plan.
See footnote
The Residents also argue with respect to the cost of extending the sewer
main, particularly in their reply brief, that the City breached the fiscal plan
by making the construction of a sewer service extension dependent upon [Residents] first
paying the costs associated with providing the sewer mains. Reply Brief p.
3. We have already observed from the full text of the fiscal
plan regarding sanitary sewer service that the Residents were always expected to pay
for the cost of this service. To the extent Residents now claim
that a municipality cannot charge the cost of extending sewer service to the
residents of an annexed territory, notwithstanding Indiana Code Section 36-9-23-29, such a claim
should have been raised in a remonstrance challenging the annexation ordinance and/or fiscal
plan. No remonstrance was filed within the sixty-day-after-adoption time limit of Indiana
Code Section 36-4-3-11, and thus Residents are precluded from attacking the validity of
the annexation and the accompanying fiscal plan, which requires the Residents to pay
for any extension of sewer service.
See Albion Natl Bank v. Department
of Financial Institutions, 171 Ind. App. 211, 219-20, 355 N.E.2d 873, 878 (1976)
(holding a collateral attack on annexation may be maintained only where annexation was
made by a body or tribunal acting without jurisdiction or power to make
the annexation, and is not available as to alleged errors, irregularities, and informalities
not going to the jurisdiction of the tribunal).
The Residents also claim entitlement to disannexation because the City has not provided
them with a sanitary sewer system, and Indiana Code Section 36-4-3-16(b)(2) permits disannexation
if the municipality has not provided police protection, fire protection, sanitary sewers, and
water for human consumption within the specific time limit for implementation . .
. . (Emphasis added.) Here, the Residents ask us to interpret
the statutory term and to mean or, and that by the Citys not
providing one of the enumerated services i.e., sanitary sewers they are
entitled to disannexation . Even if we were to accept the argument that
a plaintiff may be granted disannexation if a municipality has failed to provide
any, as opposed to all, of the four listed services, the Residents here
are not entitled to disannexation under this subsection as a matter of law.
We ordinarily endeavor to give words appearing in a statute their plain and
ordinary meaning, absent a clearly manifested legislative purpose to do otherwise. Department
of Natural Res. v. Town of Syracuse, 686 N.E.2d 410, 412 (Ind. Ct.
App. 1997). Additionally, statutory provisions covering the same general subject matter are
in pari materia and should be construed together to produce a harmonious statutory
scheme. WorldCom Network Serv., Inc. v. Thompson, 698 N.E.2d 1233, 1238 (Ind.
Ct. App. 1998), trans. denied. We also seek to harmonize our reading
of a statute with precedent of our supreme court. See Black v.
ACandS, 752 N.E.2d 148, 152 (Ind. Ct. App. 2001), trans. pending. Here,
we conclude, based on the entirety of the annexation statutory scheme and precedent
of our supreme court, that although a municipality must provide sanitary sewers to
an annexed territory, provide necessarily means to provide in a manner similar to
that in which sanitary sewers are provided to the rest of the municipality.
Acceptance of the Residents construction of Indiana Code Section 36-4-3-16(b)(2) would lead to
the requirement that all annexing municipalities must actually construct sanitary sewers in an
annexed territory or else face disannexation. Indiana Code Section 36-4-3-13(d)(5), however, merely
provides that services of a capital improvement nature, such as sewer facilities, must
be provided to the annexed territory in the same manner such services are
provided elsewhere in the municipality. It does not absolutely require the extension
of sanitary sewers to an annexed territory. Moreover, in Chidester v. City
of Hobart, 631 N.E.2d 908 (Ind. 1994), our supreme court clearly indicated that
an annexing municipality has no absolute duty to provide sanitary sewers to an
annexed territory. In that case, the City of Hobart contained large areas
that were served by septic systems as opposed to sanitary sewers, and it
was acceptable that the annexation fiscal plan simply provided that the same policy
regarding whether sanitary sewers are extended to a certain area would be applied
to the annexed territory; the fiscal plan contained no assurance that sanitary sewers
actually would be extended to the annexed territory. Id. at 912.
As the City of Hobart did in Chidester, the City of Bloomington has
decided to apply a municipal policy regarding extension of sewer service to an
annexed territory, namely USB Rule 13. It logically follows that if a
municipality is not required by statute or supreme court precedent to extend sanitary
sewer service to an annexed territory, a plaintiff cannot obtain disannexation solely on
the ground that sanitary sewers in fact were not extended. Here, the
designated evidence indicates the City provided sanitary sewers to the Residents in a
manner similar to that in which sanitary sewers were provided to the rest
of the City. The Residents are not entitled to disannexation pursuant to
Indiana Code Section 36-4-3-16(b)(2).
After examining the statutory scheme, we find the existence of legislative intent
that a plaintiff seeking disannexation and the granting of other relief under Indiana
Code Section 36-4-3-16 carries a heavy burden, once an annexation has become final
after the time period for remonstrating has passed, or a remonstrance has been
rejected. Such relief is not impossible to obtain, but there must be
a showing of egregious action (or a lack of action) on the part
of the annexing municipality, such as the treating of the annexed territory differently
from other parts of the municipality, a complete failure to provide basic municipal
services, or a failure, without justification, to implement the terms of the annexation
fiscal plan. We find that no genuine issue of material fact exists
that would support disannexation of the Residents properties under any of these theories,
and thus we conclude that the City is entitled to judgment as a
matter of law.
SULLIVAN, Judge, concurring
I concur but with a slight caveat.
I do not agree with the majority, as stated on page 13 of
the slip opinion, that the Residents ask us to interpret the statutory term
and to mean or. They are, however, stating that they are entitled
to disannexation because the City has failed to provide one of the enumerated
services i.e., sanitary sewers. Id. This contention by the Residents is
undoubtedly drawn from use of the word and in the disannexation statute itself.
That provision states that disannexation is permissible if the City has not
provided all of the enumerated services. Thus the absence of any
one of the services is a failure to provide all of the services
as required by use of the conjunctive and.
That services of a capital improvement nature, including street construction, street lighting, sewer
facilities, water facilities, and stormwater drainage facilities, will be provided to the annexed
territory within three (3) years after the effective date of the annexation in
the same manner as those services are provided to areas within the corporate
boundaries, regardless of similar topography, patterns of land use, and population density, and
in a manner consistent with federal, state, and local laws, procedures, and planning
criteria. . . .
Ind. Code § 36-4-3-13(d)(5).