Attorneys for Appellant
Attorneys for Appellees
Steven S. Hoar Angela L. Freel
Evansville, Indiana James D. Johnson
R. Steven Krohn
Don L. Smith James E. Stoltz
Nashville, Tennessee Robert F. Stayman
Evansville, Indiana
Jerry D. Stilwell
Princeton, Indiana
______________________________________________________________________________
No. 26S01-0307-CV-349
v.
_______________________________
Appeal from the Gibson Circuit Court, No. 26C01-0111-CP-142
The Honorable Keith A. Meier, Special Judge
_________________________________
On Petition To Transfer from the Indiana Court of Appeals, No. 26A01-0209-CV-345
_________________________________
February 4, 2004
The contract between MPACT and Flying J is an American Institute of Architects
(AIA) Standard Form Agreement Between Owner and Contractor (General Contract). Articles 1
and 9 of the General Contract incorporate by reference the AIA General Conditions
of the Contract for Construction (General Conditions), and the General Conditions contain an
arbitration clause. However, the subcontracts were not AIA standard form contracts but
instead were contracts prepared by MPACT. After approximately six months of preparing
for litigation, MPACT filed a motion to stay litigation and compel arbitration.
The trial court summarily denied its motion. The Court of Appeals reversed
in part, granting the motion as to Flying J, and affirmed in part,
denying the motion as to the Subcontractors. MPACT Constr. Group, LLC v.
Superior Concrete Constructors, Inc., 785 N.E.2d 632, 639, 640. We reach the
same result as the Court of Appeals.
The FAA applies only if parties agree to arbitrate. The Supreme Court
has stated that both state law contract principles and federal substantive law of
arbitration apply to answering this question. First Options of Chicago, Inc. v.
Kaplan, 514 U.S. 938, 944 (1995) (state law); Moses H. Cone Meml Hosp.
v. Mercury Constr. Corp., 460 U.S. 1, 24 (1983) (federal law). In
dicta, the Court has said:
[T]he text of § 2 [of the FAA] provides the touchstone for choosing
between state-law principles and the principles of federal common law envisioned by the
passage of that statute: An agreement to arbitrate is valid, irrevocable, and enforceable,
as a matter of federal law, save upon such grounds as exist at
law or in equity for the revocation of any contract. Thus state
law . . . is applicable if that law arose to govern issues
concerning the validity, revocability, or enforceability of contracts generally.
Perry v. Thomas, 482 U.S. 483, 492 n.9 (1987) (quoting 9 U.S.C. §
2). Recently, the Court clarified this statement, declaring that laws generally applicable
to contracts may be applied to arbitration agreements, but [c]ourts may not .
. . invalidate arbitration agreements under state laws applicable only to arbitration provisions.
Doctors Assocs., Inc. v. Casarotto, 517 U.S. 681, 686-87 (1996); see also
PaineWebber Inc. v. Elahi, 87 F.3d 589, 593 (1st Cir. 1996) (referring to
Doctors Associates, the court stated the Supreme Court explained that if a state
law is applicable to contracts generally, it may be applied to arbitration agreements,
but a state law that is specifically and solely applicable to arbitration agreements
is displaced by the FAA).
The Court of Appeals, the Seventh Circuit, a federal district court applying Indiana
law, and most other federal circuit courts of appeal have concluded that state
law contract principles apply to determine whether parties have agreed to arbitrate.
St. John Sanitary Dist. v. Town of Schererville, 621 N.E.2d 1160, 1162 (Ind.
Ct. App. 1993); Gibson v. Neighborhood Health Clinics, Inc., 121 F.3d 1126, 1130
(7th Cir. 1997); Ziegler v. Whale Sec. Co., L.P., 786 F. Supp. 739,
741 (N.D. Ind. 1992); Fazio v. Lehman Bros., 340 F.3d 386, 393 (6th
Cir. 2003); Bank One, N.A. v. Shumake, 281 F.3d 507, 513 (5th Cir.
2002), cert. denied, 537 U.S. 818 (2002); Mirra Co. v. Sch. Admin. Dist.
#35, 251 F.3d 301, 304 (1st Cir. 2001); Intl Paper Co. v. Schwabedissen
Maschinen & Anlagen GMBH, 206 F.3d 411, 417 n.4 (4th Cir. 2000); Schooley
v. Merrill Lynch, Pierce, Fenner & Smith, Inc., 133 Lab. Cas. (CCH) ¶
58,234, 1997 U.S. App. LEXIS 1884, at *5 (10th Cir. Feb. 5, 1997);
PaineWebber Inc. v. Bybyk, 81 F.3d 1193, 1198 (2nd Cir. 1996).
MPACT contends, however, that whenever state law presents an obstacle to arbitration, federal
law preempts the application of state law. It argues that the Court
of Appeals, in finding no agreement to arbitrate, either misconstrued Indiana law or
properly construed Indiana law but should have applied federal law instead. The
Subcontractors respond that the FAA only pre-empts state law which requires the parties
to resolve their disputes in a judicial forum when the contracting parties have
agreed to resolve their disputes through arbitration. (Joint Br. in Resp. to
Pet. for Transfer at 6.) That is not the case here, they
argue, because there was no agreement to arbitrate.
The FAA contains no express pre-emptive provision, nor does it reflect a congressional
intent to occupy the entire field of arbitration. Volt Info. Scis., Inc.
v. Bd. of Trs. of Leland Stanford Jr. Univ., 489 U.S. 468, 477
(1989). Nevertheless, state law may . . . be pre-empted to the
extent that it actually conflicts with federal law that is, to the
extent that it stands as an obstacle to the accomplishment and execution of
the full purposes and objectives of Congress. Id. (quoting Hines v. Davidowitz,
312 U.S. 52, 67 (1941)). Preemption has been found in cases where
state statutes explicitly made certain arbitration clauses unenforceable or placed serious burdens on
the enforceability of arbitration provisions. See, e.g., Doctors Assocs., 517 U.S. at
683, 688 (finding preemption where Montana law made arbitration clauses unenforceable unless the
first page of the contract contained in underlined capital letters a statement that
the contract was subject to arbitration); Allied-Bruce Terminix Cos. v. Dobson, 513 U.S.
265, 269, 272-73, 282 (1995) (reversing Alabama Supreme Courts denial of arbitration based
on a state statute rendering predispute arbitration agreements invalid and unenforceable); Southland Corp.
v. Keating, 465 U.S. 1, 10-16 (1984) (holding invalid on preemption grounds state
statute making agreements to arbitrate franchise claims unenforceable). But no such statute
is involved here. Nor is it the case that state law is
hostile to arbitration. Indeed, Indiana policy favors arbitration. PSI Energy, Inc.
v. AMAX, Inc., 644 N.E.2d 96, 98 (Ind. 1994) (stating that Indiana was
surely among the first jurisdictions to sanction arbitration as a means of dispute
resolution as it had a law allowing arbitration before Indiana became a state
in 1816); Ind. CPA Socy v. GoMembers, Inc., 777 N.E.2d 747, 750 (Ind.
Ct. App. 2002) (Indiana recognizes a strong policy favoring enforcement of arbitration agreements.);
see also Uniform Arbitration Act, Ind. Code § 34-57-2-1 (1998).
MPACT focuses solely on the result. It is just not true, however,
that preemption occurs every time a court finds that the parties did not
agree to arbitrate. If a court, fairly applying generally applicable state law
contract principles and not singling out arbitration agreements for hostile treatment, finds that
the parties did not agree to arbitrate, then federal law does not preempt.
See Perry, 482 U.S. at 492 n.9 (A court may not, in
assessing the rights of litigants to enforce an arbitration agreement, construe that agreement
in a manner different from that in which it otherwise construes nonarbitration agreements
under state law.); Scherk v. Alberto-Culver Co., 417 U.S. 506, 511 (1974) (the
intention of the FAA was to put arbitration agreements upon the same footing
as other contracts) (quoting H.R. Rep. No. 96, 68th Cong., 1st Sess., 1,
2 (1924)).
For these reasons, we will apply Indiana law to determine whether the Subcontractors
agreed to arbitrate.
See footnote
MPACT further argues that even if Indiana law applies, the federal policy favoring
arb
itration should influence the question whether the parties agreed to arbitrate. The
Subcontractors respond that a court must first determine whether the parties generally agreed
to arbitrate disputes. (Joint Br. in Resp. to Pet. for Transfer at
2.) We agree with the Subcontractors.
Whether the parties agreed to arbitrate any disputes is a matter of contract
interpretation, and most importantly, a matter of the parties intent. AGCO Corp.
v. Anglin, 216 F.3d 589, 593 (7th Cir. 2000) (As with any contract,
the touchstone for interpreting an arbitration clause must be the intention of the
parties.). Courts in Indiana have long recognized the freedom of parties to
enter into contracts and have presumed that contracts represent the freely bargained agreement
of the parties. Trimble v. Ameritech Publ'g, Inc., 700 N.E.2d 1128, 1129
(Ind. 1998); Contl Basketball Assn v. Ellenstein Enters., 669 N.E.2d 134, 140 (Ind.
1996). Consequently, imposing on parties a policy favoring arbitration before determining whether
they agreed to arbitrate could frustrate the parties intent and their freedom to
contract. The Supreme Court has made this clear arbitration is a
matter of contract and a party cannot be required to submit to arbitration
any dispute which he has not agreed so to submit. AT&T Techs.,
Inc. v. Communications Workers of Am., 475 U.S. 643, 648 (1986) (quotations and
citations omitted); accord Homes by Pate, Inc. v. DeHaan, 713 N.E.2d 303, 306
(Ind. Ct. App. 1999).
Additionally, courts have regularly distinguished the treatment given questions of the existence of
an agreement to arbitrate and questions of the scope of an agreed-to arbitration
clause. In determining the scope of an arbitration agreement, due regard must
be given to the federal policy favoring arbitration, and ambiguities as to the
scope of the arbitration clause itself resolved in favor of arbitration. Volt,
489 U.S. at 476; accord Moses H. Cone, 460 U.S. at 24-25; Bank
One, 281 F.3d at 513-14 n.24.
See footnote Because there was already an agreed-to
arbitration clause in these cases, applying federal policy in construing the arbitration clause
would not have fru
strated the parties intent. Using the policy favoring arbitration
to decide whether the parties did in fact agree to arbitrate does not
answer the question but rather avoids having to decide it. Only after
it has been determined that the parties agreed to arbitrate their disputes does
the policy favoring arbitration play an important role. We must determine, therefore,
whether MPACT and the Subcontractors agreed to arbitrate without resort to the federal
policy favoring arbitration.
MPACT points to two clauses in the subcontracts to support its contention that
the arbitration provision was incorporated by reference into the subcontracts. The first
reads:
[Article VI(b)] The Sub-contractor acknowledges that he has read the General contract and
all plans and specifications, together with all amendments and addenda thereto, and is
familiar therewith and agrees to comply with and perform all provisions thereof applicable
to the Sub-Contractor. The intent of the Contract documents is to include
all items necessary for the proper execution and completion of the work.
The contract documents are complementary and what is required by any one shall
be as binding as if required by all. Work not covered in
the Contract documents will not be required, unless it is consistent therewith and
is reasonable [sic] inferable therefrom as being necessary to produce the intended results.
The second reads:
Contractor has heretofore entered into a General Contract with [Flying J], hereinafter called
the Owner, to furnish and pay for all necessary and required labor, materials
. . . to perform all work required . . . inclusive of,
but not limited to the project plans and specifications . . . schedules,
drawings and amendments by addenda, as prepared by . . . the Architect,
and known as Flying J Travel Plaza, which are hereby made a part
of the General Contract between the Owner and the Contractor and are hereby,
made a part of this subcontract, as applicable to the work stated therein
and pursuant to this subcontractors intent to enter into this sub-contractual agreement, with
reference to any and all of said work.
MPACT argues that these provisions, and particularly the sentence, The contract documents are
complementary and what is required by any one shall be as binding as
if required by all, show that the General Conditions, which were incorporated into
the General Contract between MPACT and Flying J, were incorporated into the subcontracts.
The Subcontractors respond, and the Court of Appeals agreed, that provisions of
the General Contract were incorporated for the limited purpose of governing the work
to be performed. They emphasize that the sentence MPACT relies on is
preceded and followed by sentences pertaining specifically to work, and that this limits
the effect of that sentence.
While the cited provisions support both arguments, the larger context suggests that the
Subcontractors construction is correct. Allied Structural Steel Co. v. State, 148 Ind.
App. 283, 288, 265 N.E.2d 49, 52 (1970) (The true meaning of a
contract is to be ascertained from a consideration of all its provisions, and
a liberal or technical construction of an isolated clause should not be indulged
to defeat the true meaning.); Gen. Ins. Co. of Am. v. Hutchison, 143
Ind. App. 250, 254, 239 N.E.2d 596, 598-99 (1968) (It is the general
rule of law in our State that words, phrases, sentences, paragraphs and sections
of a contract cannot be read alone.). Of particular importance is the
language surrounding Article VI(b). Not only do the sentences within that provision
specifically discuss the work to be performed, but all other provisions in the
article of which it is a part relate to the work to be
performed. Clause (a) of Article VI requires that the Subcontractor supply adequate
tools, appliances, and equipment, [and] a sufficient number of properly skilled workmen to
ensure that the work gets done efficiently and promptly. Clause (c) discusses
the Architects control over the work to be performed. Clause (d) addresses
the Subcontractors need to get permits and licenses. Taken as a whole,
this article is about the work to be performed and nothing more.
If the parties intended to bind the Subcontractors to arbitration, logic dictates that
an incorporation by reference clause clearly apply to the entire contract or
be in a separate section on rights and remedies or at least with
contract provisions on liability and indemnification rather than with provisions relating to
the work.
Other provisions are telling as well, though not conclusive. Article 5.3.1 of
the General Conditions states:
By appropriate agreement, written where legally required for validity, the Contractor shall require
each Subcontractor, to the extent of the Work to be performed by the
Subcontractor, to be bound to the Contractor by terms of the Contract Documents,
and to assume toward the Contractor all the obligations and responsibilities which the
Contractor, by these Documents, assumes toward the Owner and Architect. Each subcontract
. . . shall allow to the Subcontractor, unless specifically provided otherwise in
the subcontract agreement, the benefit of all rights, remedies and redress against the
Contractor that the Contractor, by the Contract Documents, has against the Owner.
Viewing this provision with the language of the subcontract that, [t]he Sub-contractor acknowledges
that he has read the General contract . . . and is familiar
therewith and agrees to comply with and perform all provisions thereof applicable to
the Sub-Contractor, suggests that the Subcontractors are required to submit to arbitration.
The Subcontractors agreed to comply with provisions of the General Contract applicable to
them, and Article 5.3.1 of the General Conditions, as part of the General
Contract, is applicable to subcontractors. Although Article 5.3.1 was probably intended to
bind subcontractors directly, the language itself puts the burden on the contractor to
obtain an agreement from subcontractors to assume the same responsibilities as the contractor
assumes toward the owner. A comment from the American Institute of Architects,
drafters of the General Conditions, provides some guidance. It first states, A
basic requirement of the contract is that subcontractors be bound by the terms
of the contract documents. AIA Document A401 Standard Form Agreement Between Contractor
and Subcontractor, so provides. Am. Inst. of Architects, A201 Commentary (1997).
But the next sentence reads, If other subcontract forms are utilized, care must
be taken to coordinate them with Subparagraph 5.3.1. Id. This indicates
that if the general contractor uses subcontract forms other than those provided by
the AIA which MPACT did in this case it must in
its own contract include a provision requiring the subcontractors to assume the same
responsibilities that it assumes toward the owner.
MPACT may well have believed the language it used was sufficient to bind
the Subcontractors to arbitration. It cites several cases to support its contention
that the language in its subcontracts validly incorporated the arbitration clause by reference.
The Subcontractors respond that all of those cases can be distinguished from
this one. Uniroyal, Inc. v. A. Esptein & Sons, Inc., 428 F.2d
523, 524 (7th Cir. 1970) (in section of contract discussing general obligations, the
subcontract stated that the subcontractor agrees to assume toward [the contractor] all the
obligations and responsibilities that [the contractor], by those documents, assumes toward the Owner,
and that [i]n the matter of arbitration, their rights and obligations and all
procedure shall be analogous to those set forth in this Contract); Kvaerner ASA
v. Bank of Tokyo Mitsubishi Ltd., 210 F.3d 262, 265 (4th Cir.
2000) (subcontract used the phrase the the same rights and remedies and in
a provision concerning default); Maxum, 779 F.2d at 979 (subcontract stated that the
Subcontractor shall be bound by, and expressly assumes for the benefit of the
Contractor, all obligations and liabilities which the Contract Documents impose upon the Contractor);
Exch. Mut. Ins. Co. v. Haskell Co., 742 F.2d 274, 275 (6th Cir.
1984) (Subcontractor hereby assumes the same obligations and responsibilities with respect to his
performance under this Subcontract, that Contractor assumes towards Owner . . . .);
J.S. & H. Constr. Co. v. Richmond County Hosp. Auth., 473 F.2d 212,
213-14 n.3 (5th Cir. 1973) (Subcontractor agrees to be bound to the Contractor
by all of the terms of the agreement between the Contractor and the
Owner and by the Contract Documents and to assume toward the Contractor all
of the obligations and the responsibilities that the Contractor by those instruments assumes
toward the Owner.); Vespe Contracting Co. v. Anvan Corp., 399 F. Supp. 516,
520 n.4 (E.D. Pa. 1975) (Subcontractor . . . shall assume towards Contractor
all the obligations and responsibilities that the Contractor . . . assumes towards
Owner.). We agree that these cases are distinct from the case here.
In all of the other cases, the language incorporating the arbitration provision
is more clear and explicit than in the subcontracts here.
See footnote
Courts are required to give effect to parties contracts and to do so,
courts look to the words of a contract. In contracting, clarity of
language is key. Here, however, provisions in the subcontracts support both arguments,
at least in part. When there is ambiguity in a contract, it
is construed against its drafter.
Philco Corp. v. Automatic Sprinkler Corp. of
Am., 337 F.2d 405, 408 (7th Cir. 1964); Smith v. Sparks Milling Co.,
219 Ind. 576, 603, 39 N.E.2d 125, 135 (1942); Bicknell Minerals, Inc. v.
Tilly, 570 N.E.2d 1307, 1313 (Ind. Ct. App. 1991), trans. denied. In
this instance, the AIA Standard Form of Agreement Between Contractor and Subcontractor was
not used. MPACT instead drafted its own subcontracts. It was therefore
MPACTs responsibility to ensure that its subcontracts conformed to the requirements of the
General Conditions and incorporated the arbitration clause. MPACT did not do so.
The problem in this case seems to have resulted from poor contract drafting
and inadequate contract negotiations. Each side believed at the time of contract
execution that the contract provided for what it wanted in MPACTs case,
for arbitration, and in the Subcontractors case, not for arbitration. Regardless, it
is clear that arbitration was not sufficiently discussed by the parties. This
leads to one conclusion, that there was no meeting of the minds between
the parties on the issue of arbitration. Consequently, we find that there
was no agreement to arbitrate between MPACT and the Subcontractors and the Subcontractors
are not required to arbitrate their disputes with MPACT.
MPACT also sought arbitration of its disputes with Flying J. The Court
of Appeals found that the disputes were governed by the arbitration provision in
the General Conditions of the General Contract, and held that MPACT was entitled
to arbitration with Flying J. We summarily affirm the Court of Appeals
on this point. Ind. Appellate Rule 58(A)(2).
Some facts suggest that MPACT may have waived its right to arbitrate by
actively participating in the litigation. Ernst & Young LLP, 304 F.3d at
757-58; St. Marys Med. Ctr., 969 F.2d at 589. MPACT filed a
cross-claim against Flying J for breach of contract and filed cross- and counterclaims
against Flying J and the Subcontractors to foreclose its own mechanics lien.
MPACT also participated in telephone conferences and a scheduling conference where summary judgment
deadlines and a trial date were set.
The filing of counterclaims and cross-claims does not always indicate active participation in
litigation. While all cross-claims are permissive, some counterclaims are compulsory, that is,
a party must bring them or waive them. Ind. Trial Rule 13.
A party should not be held to have waived its right to
arbitrate when, in response to a complaint filed against it, it raises counterclaims
in order to preserve them. Cf. Underwriting Members of Lloyds of London
v. United Home Life Ins. Co., 549 N.E.2d 67, 71 (Ind. Ct. App.
1990) (stating that participation in discovery did not result in a waiver of
arbitration because defendant was required by court order to do so), adopted by,
563 N.E.2d 609 (Ind. 1990). MPACTs counterclaims in this case are compulsory.
The cross-claims are not, and to that extent, MPACT could be seen
as actively participating in the litigation. But that alone is not sufficient
to establish a waiver, particularly in light of the other facts.
In its answer filed March 29, 2002, MPACT stated that it was not
waiving its right to arbitration and in its affirmative defenses, requested that the
claims be submitted to arbitration. St. Marys Med. Ctr., 969 F.2d at
589 (finding that defendant waived the right to arbitrate because in the ten
months that passed since being sued, defendant filed a motion to dismiss or
for summary judgment and then did not raise arbitration until losing its motion);
Kilkenny, 733 N.E.2d at 987 (This is clearly not a case where a
request for arbitration was plead in the initial complaint and then not again
asserted until discovery was complete or an unfavorable result on the individual claims
was imminent.); Lloyds, 549 N.E.2d at 71 (finding no waiver because defendant asserted
its right to arbitrate throughout the proceedings). MPACT also did not file
motions to dismiss or for summary judgment before asserting its right to arbitrate.
These facts show that MPACT acted consistently with its right to arbitrate,
if it had one, and so its actions would not have constituted a
waiver of that right.
Dickson and Rucker, JJ., concur.
Boehm, J., dissents with a separate opinion in which Shepard, C.J., joins.
Boehm, J., dissenting.
I respectfully dissent. This is a typical multiparty construction litigation, where various
parties are pointing fingers in various directions and claiming that whatever went wrong
with the project is somebody elsesanybody elsesproblem. I agree that state law
governs the formation of the contract and that nothing in the Federal Arbitration
Act requires that these disputes between subcontractors and the general contractor be arbitrated
unless the parties agreed to that method of dispute resolution. I believe,
however, that these agreements do call for arbitration of the entire multiparty dispute
among the owner, the general contractor, and these several subcontractors.
The agreement between the general contractor and the owner is a standard printed
form AIA construction agreement. All agree that that contract includes an enforceable
arbitration clause, and an undertaking to bind subcontractors to the same terms that
obligate the general. The generals agreements with the subs provide that each
sub acknowledges the principal agreement and agrees to be bound by it.
The principal agreement provides, inter alia, that the general will impose conforming conditions
on all subs. These agreements are among businesses fully familiar with this
sort of arrangement, and fully cognizant that the last thing either the general
or the owner wants is piecemeal litigation with different subs. The result
the majority reaches produces an arbitration between the owner and the general and
litigation with one or more subs in a separate forum. The majority
concedes that the general intended to bind the subs to arbitration, but points
to imprecision in the language used to accomplish that. It seems to
me that the subs did understand, or should have, that arbitration was intended.
They should be held to have accepted arbitration when they accepted these
agreements. Accordingly, I would require arbitration of this entire dispute in one
proceeding.
The majority points to what I agree is less than elegant phrasing of
the agreement, and what it describes as inadequate contract negotiations. I think
these agreements, given the context, were sufficient to make clear to the subs
that they were expected to arbitrate their disputes with the general or the
owner. Particularly in an industry where arbitration is widely used, ambiguity does
not necessarily lead to the conclusion that no meeting of the minds occurred.
Rather, I would conclude that ambiguity should be construed in favor of
finding an agreement to arbitrate where that is commonplace in the industry.
We have on several occasions expressed support for the policy under Indiana law
favoring arbitration. PSI Energy, Inc. v. AMAX, Inc., 644 N.E.2d 96, 99
(Ind. 1994); Sch. City v. East Chicago Fedn of Teachers, Local No. 511,
622 N.E.2d 166, 169 (Ind. 1993). These rulings also support finding an
agreement to arbitrate where the documents support that conclusion, albeit with less than
precision.
Shepard, C.J., joins.