FOR PUBLICATION
ATTORNEYS FOR APPELLANT
: ATTORNEYS FOR APPELLEES:
GEORGE T. PATTON, JR. TERRILL D. ALBRIGHT
ANDREW M. McNEIL JOSEPH H. YEAGER, JR.
BRYAN H. BABB
Baker & Daniels
SANDRA H. PERRY Indianapolis, Indiana
Bose McKinney & Evans, LLP
Indianapolis, Indiana
JOHN L. RICE, Pro Hac Vice
SCOTT E. PICKENS, Pro Hac Vice
JOSEPH F. COYNE, Pro Hac Vice Pillsbury Winthrop LLP
PAUL S. MALINGAGIO, Pro Hac Vice Washington, DC
Sheppard Mullin Richter & Hampton LLP
Los Angeles, CA
ANTHONY J. TRENGA, Pro Hac Vice
Miller & Chevalier, Chartered
Washington, DC
IN THE
COURT OF APPEALS OF INDIANA
NORTHROP CORPORATION, )
NORTHROP AIRCRAFT DIVISION, )
)
Appellant-Defendant, )
)
vs. ) No. 49A02-0205-CV-428
)
GENERAL MOTORS CORPORATION and )
ALLISON ENGINE COMPANY, INC., )
)
Appellee-Plaintiffs. )
APPEAL FROM THE MARION SUPERIOR COURT
The Honorable Gary L. Miller, Judge
Cause No. 49D05-9902-CP-154
April 27, 2004
OPINION - FOR PUBLICATION
DARDEN, Judge
Did the trial court commit reversible error in instructing the jury?
Did the trial court err by awarding Allison prejudgment interest?
The design of Northrop's stealth aircraft was unique in that the aircraft's engines
were embedded within the ATF's body. Utilizing this design, the engine's high-temperature
exhaust, around 4000 degrees, would flow in a channel over the rear deck
of the aircraft, thus reducing radar and infrared observability. A key to
the success of the design was the development of an engine exhaust liner
(EEL), which is an insulating structure that would allow the aircraft to withstand
the heat produced by the ATF's engines.
In mid-1987, Northrop at first contracted with P & W and GE in
order to do some design work on the EELs. However, Northrop subsequently
felt that it may be better served subcontracting the EEL development work because
the engine companies may have been too consumed with the engine competition.
On August 17, 1987, Northrop issued requests for proposals (RFP) to Allison and
Rohr Industries, Inc (Rohr). This request incorporated product function specification (PFS)
See footnote and
statement of work (SOW)See footnote information about the liner environment and work to be
performed developing the EEL. The RFP explained that the parties were to
submit firm fixed prices for the development of the EEL and any questions
regarding errors, ambiguities or inconsistencies in the RFP should be brought to Northrop's
attention immediately. Northrop also provided Allison and Rohr with the PFS and
SOW. None of the documents included any pressure/shock data nor did either
company note the need for such data. Allison and Rohr had nine
days to review the data and submit a proposal.
Rohr submitted a proposal to Northrop priced at $4 million, and Allison submitted
a proposal priced at over $13 million. Northrop evaluated the two proposals
and accepted the Allison bid, finding that Rohr's proposal was "technically unacceptable."
Record at 7085. The Rohr proposal called for a liner weighing 308
pounds, which was over twice the weight of the liner proposed by Allison.
Northrop and Allison entered into negotiations for development of the EEL. Although
Allison had originally proposed a contract with a repricing option, it agreed to
develop the EEL at a firm fixed price, regardless of which final design
was chosen for the EEL. The contract between Northrop and Allison also
contained numerous provisions requiring Allison to provide notice to Northrop of any changes
in the scope of the work. The most significant of these provisions
incorporated Federal Acquisition Regulation (FAR) 52.24[3]-7, a notification of changes requirement, into the
contract.
Allison asserts that Northrop was in the best position to accurately predict the
engine exhaust conditions that the liner would have to meet and that Northrop
had generated voluminous test data regarding those test conditions which was unavailable to
Allison. Allison also asserts that the information which Northrop provided was incomplete
and misleading. In fact, according to Allison, Northrop had conducted years of
simulations and tests in conjunction with the government, generating extensive data critical to
the design and pricing of the EEL. However, Allison claims that when
it described an original plan for design of the liner to Northrop in
August of 1987, albeit before Allison submitted a bid for the project, Northrop
did not inform Allison that it had test data indicating that Allison's perception
of the liner environment was wrong.
On October 29, 1987, Allison personnel attended a meeting with GE representatives to
discuss the EEL. A GE engineer showed Allison a chart which appeared
to be based upon Northrop test data. The chart indicated to Allison
that the liner environment would be significantly different than had been indicated by
Northrop, and Allison engineers knew that the information would force Allison to develop
a heavier and more expensive liner design.
After seeing the chart, Allison immediately asked Northrop for all of the relevant
data, emphasizing the importance of the information and the fact that this was
a potentially catastrophic situation. Northrop responded a few days later by providing
Allison with a few charts, but they contained only a fraction of the
information which Allison required. The new information, however, did indicate that Northrop's
original specifications were in error and that the GE chart was accurate.
Allison continued to pressure Northrop for information, and its understanding of the EEL
environment gradually increased. Finally, Allison began to develop a new liner concept,
known as a honeycomb-tile design, in order to accommodate the newly-discovered environment.
Never, however, did Allison provide Northrop with a written notification of changes in
the scope of the contract as required by FAR 52.24[3]-7.
Northrop asserts that the charts which Allison saw at GE were not significant
to Allison because of the fact that they showed the pressure levels that
the EEL would experience but that the charts indicated that the EEL might
be operated in over expanded or under expanded conditions. According to Northrop,
Allison believed that this expansion could cause high pressure/shock levels in excess of
those that Allison had assumed based upon P & W data. Northrop
further asserts that Rohr's engineers, as well as the P & W engineers
with whom Allison met, testified that they knew that the ATF engines would
operate in such conditions. Finally, Northrop asserts that all supersonic jet engines
operate in over and under expanded conditions and therefore have pressure/shock levels in
the engine exhaust stream.
This suit ensued in September of 1991. On June 20, 1995, the
trial court entered the first of many entries on Northrop's various motions for
summary judgment.
Reviewing the trial court's grant of summary judgment, we held
that the trial court erroneously granted summary judgment as to counts three [superior
knowledge], four [changes in the scope of work], and six [defective specifications].
Both count three and count six allege causes of action which under California
law may be brought against private defendants. The trial court also erred
in determining that the FAR provision is inoperable without written notice.
Id. at 142.
We also determined that federal law would apply to the specialized terms of
the contracts as set out in the FARs, and that California law would
control the resolution of the common law causes of action. Id. at
134-35.
Pursuant to remand, a thirty-day jury trial began on January 22, 2002 in
the Marion County Superior Court on the remaining issues. After weighing the
evidence, the jury returned verdicts for Allison on all counts related to the
EEL and the Trailing Edge (TE)
See footnote in the amount of $25,850,434 and $5,427,862,
respectively. Thereafter, the trial court, pursuant to California Code § 3287(a), awarded
Allison prejudgment interest in the amount of $36,391,196.05. The trial court determined
that, alternatively, under California Code § 3287(b), it could have awarded prejudgment interest
in the amount of $33,266,396.80.
During the course of the trial, the jury heard testimony from dozens of
witnesses and reviewed hundreds of pages of documentary exhibits. All issues were
vigorously contested between Allison and Northrop. Virtually all of the FACTS as
found in
General Motors Corp., supra, were presented to the jury during the
course of the trial. The ensuing additional facts and evidence were presented
to the jury before arriving at its verdict.
The jury heard evidence that the determination of pressure levels was critical to
the ATF's development for several reasons. First, if the engine's thrust could
be fully expanded through the nozzle, then the engine would have achieved maximum
possible thrust. Second, the high-pressure environment generated on the aft deck would
result in a high rate of heat transfer from the exhaust to the
aircraft's frame, requiring a more robust solution to protect the ATF's frame.
Thus, in order to determine the type of environment in which the EEL
would have to operate, Northrop conducted a series of classified tests beginning in
June 1985. After the first series of tests (the 505 test) were
completed, Northrop compiled a report revealing that pressures along the nozzle and aft
deck were high and variable depending on the operating conditions.
See footnote
In March 1986, Northrop conducted another series of tests (the 505-A test).
These tests again simulated environmental conditions at subsonic and supersonic speeds. Northrop
compiled another report showing that pressures remained high and variable along the aft
deck. Later, in August 1986, Northrop conducted more tests (the 505-II test)
on the nozzle and aft deck to measure the pressure levels and cooling
effectiveness to assist it in designing and developing an aft deck for the
aircraft. Northrop prepared another report that showed that the pressure levels continued
to remain high and variable along the aft deck.
In January 1987, Northrop commenced yet another series of tests (the 520 test).
These tests were also designed to measure pressure levels. However, the
results of the tests again revealed that the pressure levels were sometimes high,
depending on the operational environment. Later, in the spring of 1987, Northrop
tested another liner that it was working on; unfortunately, it also failed to
withstand the extreme heat from the engine exhaust stream. There was testimony
that Northrop was desperate for a solution at this point in time.
Northrop began an anxious search for a solution to its problem and asked
P & W if it had a solution.
Having been selected to work on a prototype engine for the ATF, P
& W had enlisted Allison's help in developing its engine nozzle. P
& W informed Northrop that the only substance it was aware of that
could protect the aft deck from the heat of the engine exhaust was
a product invented by Allison called LamilloySee footnote ; P & W suggested that Northrop
contact Allison for assistance.
From August 4-6, 1987, Allison and P & W engineers had a series
of meetings to discuss design concepts for an engine exhaust liner. During
those meetings, P & W's engineers told Allison's engineers that they could assume
that the pressure could be between 15 and 20 pounds per square inch
(psi), a ratio of 1.33, or what otherwise could be termed a low-pressure
environment.
On August 7, 1987, Allison and P & W engineers presented design concepts,
including their assumptions about low-pressure along the aft deck, to Northrop. The
concept rated most able to withstand the exhaust environment was the "pillow concept."
(Tr. p. 3023). Allison informed Northrop that this was a low-pressure
design based on P & W's pressure specifications. Northrop complimented their work
and suggested that they continue "thinking about it." (Tr. p. 2952).
Subsequently, Northrop decided that it would be more efficient for it to contract
directly with Allison. On August 12, 1987, Allison engineers traveled to Northrop's
headquarters in California for additional discussions concerning the EEL with a larger group
of Northrop personnel. After repeating its August 7, 1987 presentation, Allison and
Northrop discussed the pressure environment along the aft deck. Allison asked Northrop
if it had any "additional data beyond what Pratt & Whitney had given
them, . . . ." (Tr. p. 2954). Northrop responded that
it did not know anything beyond what P & W had specified.
Further, when Allison asked whether GE's engine would produce a different pressure environment,
Northrop said that there would not be any surprises and directed Allison to
go back to P & W and GE for additional data.
On September 22, 1987, Northrop notified Allison by letter that it had been
selected "as the subcontractor for the development, manufacture, and delivery of the YF-23
Exhaust Liner." (Pl. Ex. 263 p. 1). The contract and its
incorporated exhibits "provide the total description, detail schedule, and terms & conditions for
performance of authorized efforts. The total fixed price for this effort is
$11,876,198."
Id.
On October 29, 1987, personnel of Allison and Northrop attended a meeting with
GE representatives to discuss the EEL. GE was also under contract with
Northrop to work on engine exhaust liner concepts. While GE presented Northrop
with the results of its work, it mentioned that its design took into
account wide pressure variations within the exhaust stream. Allison became aware at
this point that GE's design was inconsistent with its low-pressure design and assumptions,
and engaged GE's engineers in a discussion about the pressure environment. GE's
engineers produced data from Northrop's test series showing wide pressure variations. After
the meeting, Allison's design coordinator, Larry Junod (Junod), asked John Shupek (Shupek), a
Northrop heat transfer specialist, if Allison's pillow-tile design was going to be exposed
to high pressure. Shupek stated that high pressure was possible but that
he would have to talk with other people to make sure. Junod
explained, "[T]hat could be devastating. We have to have all of that
data that you have on that subject because if that sort of thing
is going to happen, our concept won't work and we're going to have
to start over." (Tr. p. 3046).
The next day, upon returning to Indianapolis, Junod impressed upon Shupek how critical
it was for Allison to understand the pressure environment. Junod asked Shupek
if the data GE presented was Northrop's data, and Shupek confirmed that the
data came from tests Northrop had conducted. Shupek also confirmed that there
was more data. Junod then requested all data that Northrop had concerning
the pressure environment on the aft deck. Shupek warned Junod that the
data was classified and that certain steps would have to be taken to
insure that the data was distributed properly.
On November 3, 1987, Shupek sent Allison a nine-page letter containing "selected liner
pressure data that Northrop obtained from the Fluidyne Model 505 II and Model
520 test series." (Pl. Ex. 290). The data confirmed Allison's concerns
about pressure variations on the aft deck. In computer simulations, Junod entered
Northrop's data in the "model of the pillow tile to see what kind
of stresses would be generated and to see whether it would fail; and
indeed it did." (Tr. p. 3050). He attempted to make variations
in the pillow tile, including thickening the tiles, but the concept failed to
withstand the high heat and pressure. Believing that the limited data in
the nine-page letter was insufficient to begin designing a new liner, Allison continued
pressuring Northrop to release all pressure data.
During November and December of 1987 and January 1988, Allison employees, Junod and
Edward Turner (Turner), had a series of meetings with Northrop employees Tom Jannetta
(Jannetta), lead engineer for exhaust system integration; Marty Bradley (Bradley), a propulsion analyst
who helped setup the 505 and 505-II tests; and Brad Bergman (Bergman), an
engineer doing work in fluid dynamics. During these discussions, Junod and Turner
"came to find out" about numerous pressure tests conducted by Northrop at Fluidyne
and NASA's facilities in Virginia and California. (Tr. p. 3056). Northrop
personnel then explained that certain design features would prevent operating the engines in
a fully expanded or low-pressure condition, as was its original intention. Using
the data from these tests and the computer simulations developed by Bergman, they
jointly began developing a pressure specification by which Allison could design an effective
EEL.
In the meanwhile, on November 20, 1987, Bob Paris (Paris), a Northrop propulsion
engineering consultant, had sent Northrop a memorandum stating that although the decision to
use Allison's Lamilloy tiles had accelerated the acoustic testing program, the ATF program
still remained a "high risk development program." (Pl. Ex. 880.0001) (emphasis in
original). Paris noted the following items that "must be addressed immediately": (1)
all engine exhaust data must be provided to Allison immediately; (2) the preliminary
design review
See footnote should be postponed beyond January 1988 to avoid selection of a
design that was based on "incomplete data and analysis"; and (3) a fixture
for the boilerplate test scheduled for April or May 1988 should be built
as soon as possible. (Pl. Ex. 880.0001-2).
On December 18, 1987, Paris sent another memorandum noting that progress in the
design of the EEL was being made, but cautioning that lack of "knowledge
of the environment that the liner must" endure put the design program at
risk. (Pl. Ex. 881.0003). He further emphasized that "[t]wo items which
put the liner design at risk [are] the availability of engine data and
the late testing of the boilerplate liner behind an engine." (Pl. Ex.
881.0003).
Still facing a preliminary design review scheduled for January 8, 1988, Allison began
to consider a concept called the "honeycomb tile" design in November 1987.
On January 31, 1988, Paris reported to Northrop that Allison was still proceeding
with the design of the EEL without knowing the "actual engine environment as
measured behind the engine." (Pl. Ex. 884.0001). He warned that neither
engine company had given "all of the required data" to Allison. (Pl.
Ex. 884.0001). Finally, on February 12, 1988, Northrop and Allison executed a
pressure specification agreement for the EEL.
The process of designing and developing the EEL took place over the next
year and a half. During that time, according to Allison, Northrop revised
many of the specifications for the EEL. Many of the originally scheduled
test dates had to be rescheduled for later dates while Allison redesigned, redeveloped,
and rescheduled its workforce to comply with Northrop's revisions. For example, the
preliminary design review that was originally scheduled for January 8, 1988 did not
take place until March 1, 1988; the detailed design review,See footnote originally scheduled for
May 1988, did not take place until May 4, 1989; the design validation
test, originally scheduled for June 1988, did not take place until February 1989;
and the ground test of the EEL, originally scheduled for April 8, 1989,
did not take place until September 1989. However, the target date for
the first flight remained the same. Allison asserted that due to Northrop's
behavior, which caused numerous setbacks and revisions, it eventually compressed its work schedule
to a 24-hour, seven-day-a-week work schedule.
In early 1988, when Northrop and Allison could not agree as to what
the environment would be for the shoulders of the EEL, Allison informed Northrop
that it would proceed according to its understanding of the environment. Under
pressure from Northrop to stay on schedule, Allison continued with its design of
the EEL, and also began to design the shoulders of the EEL, even
though it lacked design specifications concerning the environment along the shoulders. The
only shoulder design specifications that Allison possessed were drawings of the shoulders contained
in the SOW. However, in February 1988, when Allison received computer tapes
from Northrop showing "a constantly changing cross-section," it had to build a part
to accommodate the change. (Tr. p. 3797). Northrop specifically excluded the
use of titanium, requiring Allison to develop a solution that ultimately required the
use of more expensive alloys.
In February 1988, Allison discovered that Northrop had given it erroneous engine cycle
data because the computer model that generated the data had simulated an uninstalled
engine. When Northrop later gave Allison data simulating an installed engine, Allison
realized that the pressure from the engine to the honeycomb tiles was too
low; hence, it had to modify its initial design.
There was evidence that Allison could not complete the EEL without an attachment
scheme depicting where the EEL would be secured to the aft deck.
Neither tooling nor the parts could be manufactured until this information was known,
and only Northrop had this information. Early in January 1988, Allison explicitly
requested this information so that it "could remain on schedule." (Tr. p.
3803). However, Northrop did not give this information to Allison until October
4, 1988.
In April 1988, Allison declined Northrop's request that it take on the TE
project and made an offer to sell Northrop the Lamilloy necessary for it
to develop the TE. However, Northrop insisted that Allison take on the
work. Allison acceded to Northrop, but it refused to agree to a
delivery schedule date. On June 8, 1988, Allison submitted a fixed price
proposal of $2.2 million for the TE project. Allison stated that it
was committed to meeting the delivery schedule, but that "it will be difficult
given the late start of this effort." (Pl. Ex. 388-1.0002). On
June 24, 1988, Northrop gave Allison permission to proceed with the "development, manufacture,
and delivery" of the TE. (Pl. Ex. 392-1.0001).
In order to design the TE, Allison needed to know the
operational environment of the fairings, which are shiny pieces of metal attached to
the EEL shoulders that would help secure the TE. Because Northrop did
not tell Allison if the fairings would be subjected to the 4,000-degree flames
of the exhaust stream, Allison could not begin designing a cooling system for
the TE. In the meantime, LeAnne Steen (Steen), Northrop's procurement manager, sent
a letter dated October 19, 1988 to Allison insisting that the TE be
delivered by April 7, 1989, the EEL's delivery date. (Pl. Ex. 616).
On October 29, 1988, Northrop and Allison entered into a Fairings Agreement in
which they outlined the assumptions under which Allison would proceed. Attempting to
meet the April 7, 1989 deadline, Allison continued to compress its work schedule
and moved to what it called "war-time mobilization." (Tr. p. 3830).
Northrop's manufacturing manager, Bill Reid, remained on-site at Allison, and Kurt Roedel made
monthly visits. Beginning as early as September and October of 1988, Sidney
Hudson (Hudson), Allison's director of engineering, began informing Northrop that its revisions were
going to have a cost impact on the contract's price. Because much
of Allison's work had been subcontracted to other companies, and there were outstanding
invoices and work in progress, Hudson could not come up with an accurate
figure; however, he estimated that there would be approximately a $1 million impact.
Northrop responded by instructing Allison not to inform it of any cost
impact until it had an accurate figure.
Even though by October 1988, the final design of the EEL was not
complete, Northrop demanded that Allison begin manufacturing the honeycomb tiles for the EEL
and TE. In November 1988, Northrop demanded that Allison hire an additional
subcontractor to assist in the manufacture of the honeycomb tiles; Allison hired Aerobraze
in Cincinnati, Ohio. Because Aerobraze was not familiar with Lamilloy, Allison had
to expend personnel and other resources to instruct Aerobraze in the manufacturing technique
used to produce the honeycomb tiles.
On December 16, 1988, Allison finally received the specifications for the acoustic environment
surrounding the EEL. (Def. Ex. 3298). The PFS and SOW originally
outlined the "anticipated acoustic load spectra for the engine exhaust liner . .
. for both the Pratt and Whitney and General Electric engines." (Pl.
Ex. 237.1). However, the acoustic data in the PFS and SOW had
been inaccurate.
In January 1989, Allison informed Northrop that there would be a cost overrun
in the EEL program of approximately $12 million. (Pl. Ex. 620). Northrop
was later notified that Allison had met with its attorneys and concluded that
it had grounds for a claim against the cost overruns. Because Allison's
focus was on the timely completion of the EEL and TE, it informed
Northrop that a claim would be submitted at a later date; Northrop did
not object.
On January 6, 1989, Allison informed Northrop that it was withdrawing its TE
proposal because its "latest cost estimate" for the TE was $4.4 million.
(Pl. Ex. 424-1). On January 19, 1989, Allison sent Northrop a letter
wherein it wrote that "as of December 31, 1988," Allison had spent $740,000
toward the design and development of the TE, an amount in excess of
the initial authorization amount. (Pl. Ex. 428-1).
In February 1989, the design validation test of the EEL was conducted
at P & W's test facility and was a success. After the
tests, P & W commented to Northrop that "only the Allison Lamilloy design
appears viable for aircraft use at this time." (Pl. Ex. 619).
Throughout the spring of 1989, Northrop and Allison continued to negotiate a price
for the TE. After several on-site visits, Northrop reduced the amount of
work Allison was required to devote to developing the TE, and Allison subsequently
reduced its proposal price to $3.8 million. However, Northrop refused to agree
to Allison's price.
In May 1989, Allison completed its design of the EEL. At a
meeting on May 19, 1989, Blake Wallace, Vice President and General Manager at
Allison, informed Northrop that Allison was preparing a final change order proposal that
would address the cost overruns associated with all of the numerous changes Northrop
had made to the design of the EEL.
Allison later submitted its summary of the change orders and Northrop subsequently rejected
it asserting that the changes were either requested by Allison or not identified
as changes that would have had a cost impact in Allison's proposal.
As a result of the impasse, Allison stated that it would stop work
on the TE. However, pursuant to the terms of the contract, Northrop
demanded that Allison "continue performance without disruption or interruption on this critical program."
(Pl. Ex. 454-1.0001).
Allison continued working on the design and development of the TE. As
of June 19, 1989, Allison sent Northrop expenditure profiles reflecting that actual current
costs through May 31, 1989 for the EEL and its tooling were $13,448,000.
(Pl. Ex. 692). Allison also informed Northrop it projected that by
September 1990, it would cost Northrop $26,421,000 "for the engine exhaust liner alone."
(Tr. p. 2196). In addition, the cost for the TE through
May 1989 was estimated to be $2,070,075 and projected to rise to $3,973,075
by January 1990. The total cost to complete both the EEL and
TE programs was projected to cost Northrop $31,190,000. Despite receiving notice of
these expenditure profiles, Northrop did not object or protest, but continued to pressure
Allison to maintain its schedule.
On August 28, 1989, Allison sent Northrop another funds expenditure profile indicating that
as of July 31, 1989, the estimated EEL expenditures had cost Northrop $16,833,966
and the TE expenditures had cost $3,185,504. Additional expenditure profiles were sent
on November 27, 1989, which reflected that as of October 31, 1989, the
estimated EEL expenditures had cost Northrop $26,576,786. On March 26, 1990, Allison
sent yet another set of expenditure profiles to Northrop, which estimated the total
cost of the EEL program to be $39,535,413, plus $3,355,571 for tooling costs.
At no time did Northrop object or protest the profiles or order
Allison to stop work.
The finalized version of the EEL was installed in the ATF in the
fall of 1989, and successfully passed the first test flights on October 27,
1989 and again on December 1, 1989. "Allison completed and delivered the
last of [the] nine [EELs] to Northrop on June 19, 1990." (Northrop's
Br. at 11).
On August 27, 1990, Allison sent Northrop a claim requesting reimbursement for the
increased costs it had incurred to design and develop the EEL; Allison's claim
for $29,596,414 included the costs to produce the EEL, including profit, but less
payments previously made by Northrop. In December 1990, Allison also filed a
claim requesting payment of $7,308,714 for the cost, including profit, of producing the
TE.
On February 2, 1991, Northrop informed Allison that its claims were being denied.
Specifically, Northrop stated that Allison's "view that Northrop withheld critical test data
which was available prior to contract go-ahead was unfounded." (Pl. Ex. 551.0001).
Additionally, Northrop asserted that Allison knew that the EEL would be subjected
to significant shocks, and that it had provided Allison with all relevant data.
Throughout the program, Allison contended that it had in place three government-approved computer
tracking systems to track and account costs. It also had an information
management system (IMS) and a continuing monitoring system (CMS) which tracked parts and
the amount of time employees spent working on a particular project. The
third system, Artemis, applied negotiated government rates to the parts and labor information
collected by IMS and CMS. Northrop sent a financial team to inspect
and review Allison's accounting practices, financial records and tracking system and did not
detect any unusual accounting practices.
In September 1991, Allison filed suit alleging numerous breach of contract claims.
Northrop subsequently filed numerous motions for summary judgment. On June 20, 1995,
the trial court initially denied Northrop's motion for summary judgment on all counts
except one, seeking rescission of the contract. Upon Northrop's motion to reconsider,
the trial court granted summary judgment in favor of Northrop on the remaining
counts.
As noted above, Allison appealed the trial court's grant of summary judgment in
Northrop's favor. On September 12, 1997, the Court of Appeals affirmed the
trial court's grant of summary judgment concerning rescission of the contract, but reversed
the trial court's grant of summary judgment on the remaining counts, and remanded
for trial. As a result, the remaining claims at issue for trial
were: (1) that Northrop had superior knowledge (superior knowledge claim) directly related to
fulfilling Allison's obligations under the EEL contract and that Northrop failed to disclose
that information; (2) that Northrop provided Allison with defective EEL specifications (defective specifications
claim); and (3) that Northrop made changes and refinements to the original EEL
specifications and failed to pay for the cost impact of those changes (changes
in the scope of work claim). In addition, Allison alleged that a
fixed price had never been negotiated for the work it performed on the
TE, that Northrop demanded that Allison continue to perform work as required under
the terms of the contract, and that Northrop failed to pay a reasonable
price for its work on the TE. Allison claimed damages and prejudgment
interest in the amount of $29,805,634 for the EEL and $7,308,714 for the
TE. Further, Northrop filed a counterclaim against Allison alleging that it was
entitled to $2.6 million for work that Allison did not complete on the
EEL and TE.
After hearing the evidence, the jury found for Allison on all counts related
to the EEL and TE in the amount of $25,850,434 and $5,427,862, respectively,
excluding the funds Northrop had previously paid to Allison. The jury found
against Northrop on its counterclaim.
On April 24, 2002, the trial court held a hearing at Allison's request
regarding prejudgment interest. The trial court noted that the parties agreed that
California law governed any award of prejudgment interest. On May 3, 2002,
the trial court entered its order of final judgment on the jury's verdict
and awarded prejudgment interest. The trial court found that Allison was entitled
to prejudgment interest pursuant to California Code § 3287(a) and awarded Allison $36,391,196.05
in prejudgment interest. The trial court's order indicated that, alternatively, under California
Code § 3287(b), it could have awarded Allison prejudgment interest in the amount
of $33,266.396.80. The trial court then entered final judgment against Northrop in
the amount of $67,669,492.05. On May 31, 2002, Northrop filed its notice
of appeal.
On appeal, we use the same standard of review as the trial court
in determining the propriety of a judgment on the evidence. When the
trial court considers a motion for judgment on the evidence, it must view
the evidence in the light most favorable to the non-moving party. Judgment
may be entered only if there is no substantial evidence or reasonable inferences
to be drawn therefrom to support an essential element of the claim.
Hartford Steam Boiler Inspection and Ins., 775 N.E.2d at 1133 (quoting Liberty Mutual
Insurance Co. v. Blakesley, 568 N.E.2d 1052 (Ind. Ct. App. 1991)).
When reviewing a trial court's ruling on a motion for judgment on the
evidence, we examine the evidence and the reasonable inferences most favorable to the
plaintiff from a quantitative as well as qualitative perspective. Quantitatively, evidence may
fail only where there is none at all; however, qualitatively, it fails when
it cannot reasonably be said that the intended inference may logically be drawn
therefrom. The failure of inference may occur as a matter of law
when the intended inference can rest on no more than speculation or conjecture.
Hartford Steam Boiler Inspection and Ins., 775 N.E.2d at 1133.
General Motors Corp., 685 N.E.2d at 137 (quoting Brechan Enterprises v. United States,
12 Cl.Ct. 545, 549 (1987) (citations omitted)).
It is a question for the jury as to whether Northrop was aware
of the operating facts of each of the involved claims and whether its
actions should be deemed a waiver of the notice requirements of the various
contract clauses.
H.H.O. Co., 12 Cl.Ct. 147. However, Allison might not
have been entitled to an equitable adjustment if Northrop could have shown that
it was prejudiced by Allison's failure to timely notify Northrop of a change
in the scope of work. Perry-McCall Construction, Inc. v. United States, 46
Fed. Cl. 664 (2000).
If a buyer is found to have actual or constructive notice of the
facts underlying the claim, "a constructive change issue arises for work exceeding the
scope of the contract 'if the [buyer] either expressly or impliedly ordered work
outside the scope of the contract, or if the [buyer] otherwise caused the
[contractor] to incur additional work.'"
SIPCO Services & Marine Inc. v. United
States, 41 Fed.Cl. 196, 223 (1998) (quoting Miller Elevator Co. v. United States,
30 Fed.Cl. 662, 678 (1994)). "In assessing whether the work exceeds the
scope of the contract, the court is guided by the principle that each
case shall be judged according to its own facts, considering the scope and
quality of the changes ordered and the cumulative effect of such direction on
the project as a whole." Id. at 223. The work must
have been directed by the buyer and not volunteered by the contractor.
Id.
Therefore, Federal Acquisition Regulation 52.243-7(e) allows as follows:
(e)
Equitable adjustments. (1) If the Contracting Officer confirms that [Northrop's] conduct effected
a change as alleged by [Allison], and the conduct causes an increase or
decrease in [Allison's] cost of, or the time required for, performance of any
part of the work under this contract, whether changed or not changed by
such conduct, an equitable adjustment shall be made
(i) In the contract price or delivery schedule or both; and
(ii)
In such other provisions of the contract as may be affected.
(2) The contract shall be modified in writing accordingly. In the case
of drawings, designs or specifications which are defective and for which [Northrop] is
responsible, the equitable adjustment shall include the cost and time extension for delay
reasonably incurred by [Allison] in attempting to comply with the defective drawings, designs
or specifications before [Allison] identified or reasonably should have identified, such defect.... The
equitable adjustment shall not include increased costs or time extensions for delay resulting
from [Allison's] failure to provide notice or to continue performance as provided, respectively,
in (b) and (c) above.
General Motors Corp., 685 N.E.2d at 136 (quoting 48 CFR 52.243-7).
Here, there was sufficient evidence for the jury to render a verdict in
favor of Allison on its change in scope of work claim. The
jury heard evidence that Northrop was competing with Lockheed for a future ATF
contract worth an estimated $50 billion. In addition, the Master Agreement stated,
"Time is of the essence in the performance of this Order." (Pl.
Ex. 254.0020). Specifically, Allison attempted to notify Northrop of the anticipated cost
overruns; however, Northrop instructed Allison to continue work and demanded that Allison hire
an additional subcontractor, thereby requiring Allison to expend unanticipated resources.
The Master Agreement also contained a notification clause in paragraph 5.
See footnote
Concerning
this notification clause, the jury heard testimony from Titlow, Allison's contracts administrator who
negotiated the terms within the Master Agreement. He stated that, in its
original form, paragraph 5 made Allison responsible for the costs of any changes,
but that Allison did not agree to it because it "was more business
risk than [it] could accept." (Tr. p. 2166). Titlow testified that
the purpose of the final version of paragraph 5 was to allow Northrop
to continually refine the specifications, but that Northrop had to pay for any
cost increase over $1,000. He stated that Allison did not contemplate the
notice provisions in paragraph 10 to have any impact on the changes made
under paragraph 5.
See footnote
Under cross-examination, Titlow testified that the lack of any "hard data" or the
"ill-defined specifications" could cause cost increases. (Tr. p. 2272). He also
stated that the notice provision in paragraph 10 had applied to buyer-directed changes
and not constant refinement of technical specifications. Although Avram Tucker, a financial
analyst giving expert testimony on Northrop's behalf, testified that Allison's claims were not
proper, Titlow testified that Northrop was on notice of the cost impact because
they were always informed, attended meetings, and occupied offices at Allison's headquarters.
See footnote
In fact, a Northrop progress payment authorization memorandum dated December 1989 stated that
Allison's "performance is monitored daily by Status Reports, Technical Interface Meetings and on
a monthly basis by Program Reviews." (Def. Ex. 2987.0820). When asked
why Allison did not give Northrop formal written notice of the actual cost
impact, Titlow stated that calculating the actual cost was impossible because the cost
was constantly changing because of the changes in specifications. When asked if
Allison was stretching the truth in calculating the cost impact, Titlow said that
was also impossible because government auditors were present.
Concerning Northrop's changes, the jury heard evidence of how Northrop repeatedly provided Allison
with a changing array of engine-cycle data. The jury heard testimony about
how changing engine-cycle data would mean changing the pattern of holes in the
Lamilloy and the configuration of the radiation shield and feet on the underside
of the honeycomb tiles. The record shows that as a result of
the erroneous engine-cycle data, Allison had to develop a titanium radiation shield to
fit underneath the EEL. This project had to be subcontracted to Flameco,
a Utah company. Using a process called super plastic forming, a die
was fabricated (costing over $1 million); twenty-seven titanium pieces were produced and pressed
into three configurations (costing over $1 million); and the three pieces were then
welded into a single shield for each of the nine EELs. The
record also shows that Northrop continued to make changes in the engine-cycle data
until October 1988.
In addition, the jury heard evidence that Allison had informed Northrop of its
understanding of the pressure environment along the shoulders of the EEL. Northrop
subsequently gave Allison computer tapes showing that the pressure environment along the shoulders
was constantly changing. Allison informed Northrop that it would have to manufacture
the shoulders from "either nickel-based, cobalt-based, or iron-based alloys[]" because Northrop had specifically
excluded using titanium. (Pl. Ex. 831 Tab 77). Allison informed Northrop
that this process would be time consuming and expensive.
Further, the jury heard John Daniluck (Daniluck), Allison's chief project manager, testify that
every component of the EEL was affected by several change specification memoranda and
that Allison tracked spending with an accounting system approved by the federal government.
Daniluck testified that despite Northrop's changes and delays in providing necessary information
to Allison, Northrop continued to pressure Allison to remain on schedule. Daniluck
testified that Northrop even insisted that Allison begin fabrication of the honeycomb tiles
before the acoustic test and design validation process was complete. Therefore, Allison
had to begin manufacturing of the tiles without detailed drawings, which was unusual.
Daniluck also testified that Northrop was aware of the effect these changes were
having on pricing but continued to pressure Allison to stay on schedule.
In fact, Daniluck testified that Steen, Northrop's manager of major subcontracts, threatened that
Northrop would sue "if our deliveries are late, and as a result they're
not first to fly and they lose this contract, [Northrop] will sue Allison
for a billion dollars, including [Daniluck] personally named as a defendant." (Tr.
p. 3834). Frank Gillette (Gillette), a former P & W engineering manager
responsible for the design and development of the engine, also testified that Northrop
wanted this contract "in the worst way." (Tr. p. 4162). Gillette
stated that the contract was worth an estimated $50 billion dollars because it
was expected that the Air Force would order 700 planes at an estimated
cost of $50 to $70 million each.
The jury heard evidence of how Hudson told Northrop in September and October
of 1988 that there was going to be a cost impact on the
contract's price, and how Northrop instructed Allison not to inform it of a
cost impact until it had an accurate figure. As mentioned earlier, Northrop
continued pressuring Allison to maintain its production schedule. Northrop also insisted that
Allison hire another subcontractor, Aerobraze, to facilitate the manufacturing of the tiles; this
resulted in Allison having to spend time and resources to instruct Aerobraze in
the techniques used to produce the honeycomb tiles.
The jury heard evidence that in January 1989, Allison informed Northrop that the
EEL program would have a cost overrun of approximately $12 million. (Pl.
Ex. 620). The jury was presented with evidence that Steen had met
with Titlow in June 1989 to discuss the total cost of the program,
and that Allison was submitting monthly cost expenditures to Northrop. Despite receiving
an expenditure profile in May 1989 projecting the total cost of the EEL
program to be $31,190,000, Northrop did not protest and Allison continued to meet
the deadlines set by Northrop.
As a result of the evidence presented during the trial, the jury had
sufficient evidence to find that (1) Northrop made numerous refinements to the PFS
having a cost impact greater than $1,000; (2) Northrop's conduct caused the changes;
(3) Northrop had either actual or constructive notice of the cost impact; and
(4) that Northrop failed to pay Allison for the cost of the changes
or make an equitable adjustment in the contract price. The trial court's
judgment denying Northrop's motion for judgment on the evidence is affirmed.
2.
Jury Instructions
Northrop appeals the submission of final instructions 15, 18, 20, 22,
23, 23A, 24, 29, and 34 to the jury.
"The manner of instructing the jury is committed to the sound discretion of
the trial court."
Armstrong v. Federated Mutual Insurance Co., 785 N.E.2d 284,
287 (Ind. Ct. App. 2003), trans. denied. An instruction informs the jury
of the law applicable to the facts without misleading the jury and to
enable it to comprehend the case clearly and arrive at a just, fair,
and correct verdict. Id. We will reverse only upon a showing
of an abuse of discretion. Id. "Even if we conclude that
a trial court erred in instructing the jury, reversal is not always warranted.
If we determine that the verdict would not have differed had the
jury been properly instructed, such error is deemed harmless." Id. at 287.
Further, "
It is well-established and elementary that instructions to the jury must
be viewed as a whole and construed in harmony with each other and
it is not necessary for any one instruction to contain all the law
applicable to the case." Martin v. Roberts, 464 N.E.2d 896, 902 (Ind.
1984).
That Northrop had information that was material to the pricing or performance of
the parties' EEL contract;
That the information was known or accessible only to Northrop;
That Northrop knew, or reasonably should have known, that the information was not
known or reasonably accessible to Allison; and
That the information was not disclosed to Allison before entering into the contract.
If you find that Allison proved all of these propositions by a preponderance
of the evidence, then you may find for Allison on its superior knowledge
claim and determine Allison's damages in accordance with the instructions on damages that
I will give you.
However, if you find that Allison has not proved all of these propositions,
then your verdict must be for Northrop on Allison's claim for breach of
contract for failure to disclose superior knowledge.
(Northrop's App. p. 932) (emphasis added).
Northrop argues that this instruction incorrectly states the law by stating that it
"reasonably should have known" that Allison could not have obtained the test data.
(Northrop's App. p. 932). Specifically, Northrop argues that this instruction conflicts
with this court's decision in General Motors Corp. because that language was not
included as part of the elements of the superior knowledge claim. Allison
argues that this language correctly states California's law on a superior knowledge claim.
In addition, Northrop argues that the word "disclosure" in this jury instruction "did
not come from any California case." (Northrop's Br. at 34). Northrop
asserts that California law requires that "courts give words their ordinary dictionary meaning
unless special meaning is required." (Northrop's Br. at 43). Northrop puts
forth the following definition of "disclosure" from Black's Law Dictionary (6th ed. 1991),
"to bring into view by uncovering; to expose; to make known; to lay
bare; to reveal knowledge; to be free from secrecy or ignorance, or make
known."
Here, we find that Final Instruction 15 was "technically" incorrect. However, because
the jury's verdict would not have been different, we find that the tendering
of this defective instruction is harmless error. Armstrong, 785 N.E.2d at 290
(Ind. Ct. App. 2003) (jury instruction harmless if jury verdict would not have
differed). In Warner Constr. Corp. v. Los Angeles, (1970) 2 Cal.3d 285,
the California Supreme Court found that there were three instances where non-disclosure of
material facts might support a cause of action. One of those instances
was where "the facts are known or accessible only to the defendant, and
the defendant knows they are not known to or reasonably discoverable by the
plaintiff." Id. at 294 (emphasis added). In General Motors Corp., we
cited this precedent and stated "that a duty of disclosure on the part
of Northrop would only exist if the information regarding the pressure shock environment
was known or accessible only to Northrop and if Northrop knew that this
information was not known or reasonably accessible to Allison." 685 N.E.2d at
139 (emphasis added). As a result, Final Instruction 15 should have instructed
the jury that Northrop had to have actual knowledge that the information was
not known or reasonably accessible to Allison.
However, Allison submitted evidence that Northrop had actual knowledge that the pressure-shock data
was not known or reasonably accessible to Allison. As we have mentioned,
evidence was introduced showing that Northrop's test data was more detailed than that
given to Allison by P & W; that the data was classified; and
that special procedures were necessary in order to make it available to Allison.
Having considered this evidence, we find that the jury's verdict would not
have been altered. In addition, the use of the word "disclosure"
in this instruction does not mislead the jury. As Allison's claim is
that Northrop failed to disclose its test data, it is appropriate that the
jury be instructed that Allison must prove that Northrop failed to disclose the
relevant information. As a result, Final Instruction 15 is not erroneous.
If you find that Allison proved all of these propositions by a preponderance
of the evidence, then you may find for Allison on its defective specifications
claim and determine Allison's damages in accordance with the instructions on damages that
I will give you.
However, if you find that Allison has not proved any or all of
these propositions, then your verdict may be for Northrop on Allison's defective specifications
claim.
(Northrop's App. p. 935).
Northrop argues that Final Instruction 18 was defective because it failed to tell
the jury what damages were recoverable. In essence, Northrop argues that this
instruction allows Allison to recover damages for the total cost of its work
and not solely for work performed within the contract's scope. In response,
Allison argues that other instructions cure any defect.
We find that Final Instruction 24 cures any alleged defect in Instruction 18.
See footnote
As we mentioned above, jury instructions must be "viewed as a whole
and construed in harmony with each other and it is not necessary for
any one instruction to contain all the law applicable to the case."
Martin, 464 N.E.2d at 902. Final Instruction 24 informs the jury that
the measure of Allison's damages concerning the EEL contract "is that amount which
will compensate Allison for all the loss caused by Northrop's breach and those
losses, which in the ordinary course of things, would be likely to result
from Northrop's breach." (Northrop's App. p. 943). Therefore, we find that
Final Instruction 18 is not erroneous when read in conjunction with the remaining
final instructions.
(Northrop's App. p. 937) (emphasis added).
Northrop argues that Final Instruction 20 eliminated the requirement that Allison's reliance on
the defective specifications be reasonable. Allison argues that the instruction does require
that its reliance be reasonable. Specifically, Allison asserts that the instruction requires
that a person in its position must have "reasonably considered" the information important
"in making its decisions about the contract." (Northrop's App. p. 937).
We disagree with Northrop's contention that Final Instruction 20 requires the jury to
presume Allison's reliance was reasonable. While the instruction does inform the jury
that it may presume that Allison's reliance was reasonable, it further instructs the
jury that it may only do so after having determined whether the information
Northrop gave to Allison was material. The instruction defines "material information" as
"information that a person in Allison's position might have reasonably considered important under
the circumstances in making its decisions about the contract." While this final
instruction would have been better if it defined "material information" in terms of
what Allison "would" rather than "might" have considered important, the instruction did not
mislead the jury. As a result, the instruction does require the jury
to determine whether Allison's reliance on the information was reasonable under the circumstances.
Northrop argues that Final Instruction 23A is defective because it specifically states that
Allison's superior knowledge and defective specification claims are not subject to the notice
provisions within the contract. Northrop argues that these claims are "subject to
the contract itself." (Northrop's Br. at 28).
We disagree. Notice is not an element of either the superior knowledge
or the defective specification claims.
See footnote
See San Diego Hospice, 31 Cal.App.4th 1048;
Karoutas, 232 Cal.App.3d 767; General Motors Corp., 685 N.E.2d 127. In addition,
concerning Allison's superior knowledge claim, it is unclear how Allison could have given
Northrop notice that Northrop was in possession of a material fact known or
accessible only to Northrop. San Diego Hospice, supra. Concerning Allison's defective
specification claims, it is also unclear how Allison was to give notice to
Northrop that the EEL specifications were incorrect. As the evidence indicated, Allison
was not initially aware that Northrop was in possession of the EEL pressure
data. As a result, we cannot say that Final Instruction 23A is
defective resulting in reversible error.
That there were refinements of the PFS after September 22, 1987;
That such refinements had a cost impact over $1,000; and
That Northrop failed to pay Allison an increased contract price for such refinements
to the PFS.
If you find that Allison proved all of these propositions by a preponderance
of the evidence, then you may find for Allison on its changes claim
and determine Allison's damages in accordance with the instructions on damages that I
will give you.
However, if you find that Allison has not proved any or all of
these propositions, then your verdict must be for Northrop on Allison's changes claim.
(Northrop's App. p. 939).
That Northrop's conduct effected a change to the contract;
That Northrop's conduct caused an increase in Allison's cost of performance under the
contract; and
That Northrop failed to make an equitable adjustment in the contract price.
If you find that Allison proved all of these propositions by a preponderance
of the evidence, then you may find for Allison on its changes claim
and determine Allison's damages in accordance with the instructions on damages that I
will give you.
However, if you find that Allison has not proved all of these propositions,
then your verdict must be for Northrop on Allison's changes claim.
(Northrop's App. p. 940).
Northrop argues that these instructions are defective because they relieve Allison of its
responsibility to "comply with the changes provisions in the contract as set forth
in the later instructions." (Northrop's Br. at 17). In addition, Northrop
asserts that the instructions are mandatory in that they require the jury to
find for Allison, and they nullify the notice provisions in the contract.
As a result, Northrop argues that it was prejudiced and should be granted
a new trial. In response, Allison argues that the instructions are not
mandatory because they specifically state that the jury "may" find for Allison if
Allison proves the elements by a preponderance of the evidence. Allison further
argues that instructions 23A, 23B, and 27 make clear that its changes claims
were subject to the contract notice provisions within the contract, and because Allison's
superior knowledge and defective specification claims are extra-contractual common law claims, the jury
was properly instructed that the notice provisions do not apply to those claims.
We find that Final Instructions 22 and 23 are not erroneous. It
is true, and we have noted, that a contractor's failure to adhere to
the notice provisions within a contract can result in subsequent claims being disallowed.
See General Motors Corp., 685 N.E.2d at 136-37 (citing H.H.O., 12 Cl.Ct.
at 164). Likewise, it is also true that the facts of a
given case may allow for a less technical or liberal reading of a
contract notice provisions. Id. For example, a constructive change order issue
may arise if Northrop had actual or constructive notice of the facts underlying
the claim. SIPCO Services & Marine Inc., 41 Fed.Cl. 196. In
other words, "a constructive change issue arises for work exceeding the scope of
the contract 'if [Northrop] either expressly or impliedly ordered work outside the scope
of the contract, or if [Northrop] otherwise caused [Allison] to incur additional work.'"
Id. at 223 (citation omitted). The fact finder is "guided by
the principle that each case shall be judged according to its own facts,
considering the scope and quality of the changes ordered and the cumulative effect
of such direction on the project as a whole." Id.
In this case, we find that Final Instructions 23A, 23B, and 27 eliminate
any perceived requirement that the jury disregard the Master Agreement's notice provisions.
See Martin, 464 N.E.2d 896 (jury instructions are to be read as a
whole). The instructions, read as a whole, clearly inform the jury that
they must decide (1) the parties' intentions regarding the notice provisions within the
Master Agreement; (2) whether Allison gave Northrop written notice that the changes in
the scope of work were having a cost impact; (3) whether Northrop had
constructive notice of the cost impact of the changes; (4) whether Northrop was
prejudiced by any lack of notice; (5) whether Allison is entitled to an
equitable adjustment in the contract price; and (6) whether any of Allison's recoverable
costs should be reduced by the amount of any increase in Northrop's costs
caused by Allison's failure to provide notice. As a result, these instructions
cure any alleged error.
(Northrop's App. p. 943).
Northrop argues that this instruction is defective. Specifically, Northrop argues that Final
Instruction 24 incorrectly tells the jury to award Allison the total cost of
performing under the contract. Citing Amelco Electric v. City of Thousand Oaks,
(2002) 27 Cal. 4th 228, Northrop asserts that the proper method of calculating
damages is to determine the actual cost, "where each element of extra expense
is linked to a proven breach and added up for a total award."
(Northrop's Br. at 44). Further, Northrop argues that the trial court
erroneously excluded evidence that would have shown that Allison was asserting a total
cost claim and that Allison caused much of the cost overruns through inefficiency
and mismanagement.
Allison responds by arguing that this instruction is a "standard, classic, instruction on
damages." (Allison's Br. at 83). Allison asserts that the instruction provides
that Allison should be compensated only "for all the loss caused by Northrop's
breach and those losses, which in the ordinary course of things, would be
likely to result from Northrop's breach." (Northrop's App. p. 943). Additionally,
Allison argues that California law supports the instruction as submitted to the jury.
We acknowledge that California law disfavors an award of damages under the total
cost theory. Amelco, 27 Cal. 4th 228. "Under this method, damages
are determined by 'subtracting the contract amount from the total cost of performance.'"
Id. at 243 (citation omitted). A jury may be permitted to
award damages under the total cost methodology, but the plaintiff must "establish (1)
the impracticality of proving actual losses directly; (2) the plaintiff's bid was reasonable;
(3) its actual costs were reasonable; and (4) it was not responsible for
the added costs." Id. at 243. However, even before "this method
may be used, the trial court bears the initial responsibility of determining that
each element of the four-part test set forth above can be met."
Id. at 244 (emphasis added).
Here, we find that Final Instruction 24 was not defective. First, unlike
Amelco, the jury in this case was not instructed on awarding damages based
on Allison's total cost. The instant instruction mirrors pattern California Civil Jury
Instruction 10.90, and it makes no mention of the total cost theory of
damages.
See footnote Second, although Northrop tendered to the trial court a total cost
instruction, the trial court appears to have followed
Amelco's holding by rejecting Northrop's
instruction, apparently deciding that the evidence did not warrant tendering a total cost
instruction. As a result, we cannot say that the trial court abused
its discretion or that Final Instruction 24 misled the jury. See Armstrong,
785 N.E.2d 284.
Allison and Northrop entered into a contract whereby Allison would design and manufacture
the Trailing Edge.
Allison did design and manufacture the Trailing Edge and supplied it to Northrop;
and
Allison has not been paid any amount for its work on the Trailing
Edge contract.
The parties dispute what amount of money is owed to Allison under the
Trailing Edge contract.
You are instructed that a contract such as the one between Allison and
Northrop for the Trailing Edge need not include a price to be binding.
Parties may agree to be bound by a contract even when they
otherwise dispute the price to be paid for the goods in question.
If the parties fail to agree on a price, the law provides that
the price is a "reasonable price" at the time of delivery. A
reasonable price is what a willing buyer would pay a willing seller for
the goods. Where, as here, there is no market price for the
goods, you may determine a reasonable price based on the actual cost of
the goods, plus a reasonable profit.
Allison claims that it and Northrop never agreed to a price, and that
Northrop breached the contract by failing to pay Allison a reasonable price for
the Trailing Edge at the time of delivery. Northrop, however, claims that
it and Allison did agree on a price for the Trailing Edge, and
that Allison is entitled to no more than that price.
You are instructed that you are to determine what amount Northrop owes Allison
under the Trailing Edge contract. If you find that the parties never
agreed upon a price, then Northrop is liable for breach of contract for
failing to pay a reasonable price when the Trailing Edge was delivered.
You may then determine, in accordance with these instructions, what a reasonable price
for the Trailing Edge is, and award Allison that amount as damages.
However, if you find that the parties did agree upon a price for
the Trailing Edge, then your verdict may be for Allison for the price
agreed upon.
(Northrop's App. p. 948-49).
Northrop argues that this instruction "erroneously introduced breach-of-contract themes into the [Trailing Edge]
issue, and the verdict form improperly directed a verdict for Allison." (Northrop's
Br. at 55). Specifically, Northrop asserts that the issue was not whether
the contract was breached, "but whether a price was reached and, if not,
what was the reasonable price." (Northrop's Br. at 57). Further, Northrop
argues that the verdict form erroneously read, "You must find for Allison on
the [TE] claim." (Northrop's Br. at 56). Instead, the verdict forms
should have read "for or against Allison on the [TE] claim." (Northrop's
Br. at 56). Allison argues that the instruction is a correct statement
of the issues.
We are unclear as to how Final Instruction 29 "erroneously introduced breach-of-contract themes
into the TE issue, . . . ." (Northrop's Br. at 55).
It was uncontested that Northrop failed to pay Allison for the work
it performed on the TE. As Final Instruction 30 specifically states, "What
is in dispute is how much money Northrop should pay Allison for that
work, and that is a dispute which [the jury] must resolve." (Northrop's
App. p. 950). "There is also no dispute that Northrop and Allison
had a contract for Allison to design and build nine (9) Trailing Edges
for the Engine Exhaust Liners." (Northrop's App. p. 950). Because Allison
was not paid for its work in designing and building the TE, Northrop
breached the contract. See Careau & Co. v. Security Pacific Business Credit,
Inc., (1990) 222 Cal.App.3d 1371 (
A cause of action for damages for
breach
of
contract
is comprised of the following
elements
: (1) the
contract
, (2) plaintiff's
performance or excuse for nonperformance, (3) defendant's
breach
, and (4) the resulting damages
to plaintiff.).
The only issue was the amount of damages to be
paid to Allison.
See footnote As a result, Final Instruction 29, especially when read
in conjunction with Final Instruction 30, does not mislead the jury. For
the same reasons, the challenged jury verdict forms were also correct.
(Northrop's App. p. 956).
Northrop argues that this instruction is erroneous because it is a mandatory instruction.
Northrop asserts that it is mandatory because the "trial court told the
jury that if they found Northrop withheld certain information, they could not consider
acoustics in the design shift." (Northrop's Br. at 41). Allison argues
that the survivability of the pillow-tile concept is irrelevant in determining whether Northrop's
material omissions or misrepresentations caused Allison to propose the pillow-tile design. Further,
Allison argues that Final Instruction 34 "is not a disfavored mandatory instruction because
it does not set out all the essential elements of a claim and
then direct the jury to find for a party on satisfactory proof of
all those elements." (Allison's Br. at 79).
Mandatory instructions are ones which attempt to set up a factual situation directing
the jury to a certain result. Mandatory instructions are disfavored in the
law, . . . and our courts have repeatedly cautioned trial judges about
the dangers of giving instructions which are mandatory in form. Thus, it
is well within a trial court's discretion to refuse a tendered instruction when
it can be framed to cover the principle of law without mandatory language.
Moreover, where, as here, a trial court tenders numerous final instructions, the
jury is unlikely to be misled by a one-word nuance. As our
supreme court has previously observed,
Instructing a jury is a most difficult and complex process. It is
generally conceded that there has been an overemphasis placed upon the wording and
refined meaning of instructions which far exceed their actual effect upon the jury.
When an instruction has to be read and reread by a legally
trained mind to catch a slight variation or error in its meaning, it
is difficult to believe that a jury of laymen could have been misled.
Keith v. Mendus, 661 N.E.2d 26, 37 (Ind. Ct. App. 1996), trans. denied.
(citations omitted).
Here the trial court submitted 37 final instructions to the jury, 17 of
which were related to Allison's EEL claims. As Northrop is unclear as
to what result this instruction erroneously leads the jury, we find that Final
Instruction 34, when read in conjunction with the 36 remaining instructions, was not
defective.
3. Prejudgment Interest
Northrop argues that prejudgment interest awarded under California Civil Code § 3287(a) was
improper because Allison's damages were not certain or capable of being made certain
because Northrop contested the method of calculation.
See footnote In addition, Northrop argues that
the trial court's award of prejudgment interest under California Civil Code § 3287(b)
was improper because it failed to articulate its rationale.
In response, Allison argues that prejudgment interest under § 3287(a) is available even
where Northrop disagrees with the cost of the work performed. Moreover, Allison
argues that there was no disagreement as to the basis for calculating damages.
For example, Allison asserts that Northrop never contested the accuracy of its
accounting records. Concerning the trial court award under § 3287(b), Allison argues
that this court need not address it if we find the award under
§ 3287(a) was properly imposed. Nevertheless, Allison asserts that the evidence supports
the trial court's award.
California Civil Code § 3287(a) provides:
(a) Every person who is entitled to recover damages certain, or capable
of being made certain by calculation, and the right to recover which is
vested in him upon a particular day, is entitled also to recover interest
thereon from that day, except during such time as the debtor is prevented
by law, or by the act of the creditor from paying the debt.
This section is applicable to recovery of damages and interest from any such
debtor, including the state or any county, city, city and county, municipal corporation,
public district, public agency, or any political subdivision of the state.
Subdivision (b) provides:
(b) Every person who is entitled under any judgment to receive damages
based upon a cause of action in contract where the claim was unliquidated,
may also recover interest thereon from a date prior to the entry of
judgment as the court may, in its discretion, fix, but in no event
earlier than the date the action was filed.
The trial court's order on prejudgment interest reflects its consideration of both subdivisions
of § 3287.See footnote The court determined:
Based on the evidence presented at trial,
this Court finds that Allison's damages
are certain or capable of being made certain by calculation under California [Civil]
Code § 3287(a) as of August 27, 1990 with regard to the EEL
damages and as of December 5, 1990 with regard to the Trailing Edge
damages, the dates on which Allison filed its claim for excess costs with
Northrop.
(Northrop's App. p. 95) (emphasis added).
The trial court expressly rejected Northrop's argument that the damages were not certain
or capable of being made certain because Northrop had contested Allison's method of
calculating its damages. Specifically, the court stated:
Defendant's counterclaims and claims for offsets did not make Allison's damages uncertain or
incapable of being made certain and the jury's award of damages established that
once the jury decided the appropriate scope of liability and responsibility, the jury
had the ability to calculate with precision the amount of plaintiff's damages on
the basis of financial data admitted into evidence.
(Northrop's App. p. 95-96). The trial court then determined that the jury's
entire damages award of $31,278,296 was subject to prejudgment interest under subsection (a),
as of the dates Allison presented its EEL and TE claims to Northrop.
The trial court set out an alternative basis for an award of prejudgment
interest pursuant to § 3287(b). The court also determined that the jury's
entire damages award was subject to prejudgment interest under subsection (b), commencing on
September 13, 1991 the date Allison filed this action in court.
The trial court calculated the prejudgment interest award alternatively under both subdivisions, (a)
and (b). The court specified that pursuant to California Civil Code §
3289 the prescribed prejudgment interest rate of 10% per annum would result in
a prejudgment interest award of $36,391,196.05 under subdivision (a), and a prejudgment interest
award of $33,266,396.80 under subdivision (b). Ultimately, the trial court imposed prejudgment
interest pursuant to subdivision (a), resulting in a total damages and prejudgment interest
award of $67,669,492.05.
Prejudgment interest must be awarded as a matter of right under subdivision (a);
however, prejudgment interest awards are a matter of discretion under subdivision (b).
Lewis C. Nelson & Sons v. District¸ (2001) 90 Cal.App.4th 64, 71.
Thus, the statute governing prejudgment interest mandates such an award where the amount
of the claim can be determined by established market values or by computation.
Wisper Corp. N.V. v. Calif. Commerce Bank et al., (1996) 49 Cal.App.4th
948. A defendant's denial of liability does not make damages uncertain for
the purposes of § 3287. Id. at 958. "[T]he policy underlying
authorization of an award of prejudgment interest is to compensate the injured party
to make that party whole for the accrual of wealth which could
have been produced during the period of loss." Id. at 960 (quoting
Cassinos. v. Union Oil Co., (1993) 14 Cal.App.4th 1770, 1790).
"The test for recovery of prejudgment interest under section 3287, subdivision (a) is
whether defendant (1) actually knows the amount of damages owed plaintiff, or (2)
could have computed that amount from reasonably available information." KGM Harvesting Co.
v. Fresh Network, (1995) 36 Cal.App.4th 376, 391; accord Wisper, 49 Cal.App.4th at
960. "If the defendant does not know or cannot readily compute the
damages, the plaintiff must supply him with a statement and supporting data so
that defendant can ascertain the damages." Polster, Inc. v. Swing, (1985) 164
Cal.App.3d 427, 435).
Further, "[t]he cases indicate that where there is a large discrepancy between the
amount of damages demanded in the complaint and the size of the eventual
award, that fact militates against a finding of the certainty mandated by [Civil
Code section 3287]." Wisper, 49 Cal.App. 4th at 961 (quoting Polster, 164
Cal.App.3d at 435). "Conversely, where there is no significant disparity between the
amount claimed in the complaint and the final judgment, this factor generally tends
to show that damages were certain or capable of calculation." Wisper, 49
Cal.App. 4th at 961.
Here, the jury's damages award is not significantly disparate from the amount Allison
claimed in its complaint. The evidence disclosed that Northrop had personnel in
Allison's plant, and that Allison supplied Northrop with monthly statements and the available
supporting data in order to allow Northrop to ascertain the amount owed before
Allison filed suit. Even before Allison filed its lawsuit, Northrop had sent
a financial team to inspect and review Allison's financial records and found no
unusual accounting practices or voiced any concerns about Allison's records.
Additionally, the trial court specifically referred to the "purposes and policies of §
3287," noting that "an award of prejudgment interest to the plaintiffs" would serve
those purposes and policies. (Northrop's App. p. 96). As indicated above,
one such policy is to make the damaged party whole by compensating that
party for the loss of the accrual of wealth during the period when
the damages were calculable.
Accordingly, we cannot say that the trial court erred by determining that "Allison's
damages [were] certain or capable of being made certain by calculation under California
Code § 3287(a) as of August 27, 1990 with regard to the EEL
damages and as of December 5, 1990 with regard to the Trailing Edge
damages, the dates on which Allison filed its respective claims for excess costs
with Northrop." (Northrop's App. p. 95). After the trial court so
determined, Allison was entitled to prejudgment interest pursuant to § 3287(a).
Inasmuch as the prejudgment interest award may be sustained under subdivision (a), we
need not address the trial court's alternative determination under subdivision (b).
There was sufficient evidence presented to the jury and by a preponderance of
that evidence, we find no reversible error in the jury's verdicts in favor
of Allison on its superior knowledge claim, its defective specifications claim, and its
claim for damages due to scope of work changes caused by Northrop's conduct.
There was sufficient evidence presented to the jury and by a preponderance of
that evidence, we find no reversible error in the jury's verdict in favor
of Allison on its claim for damages due to Northrop's failure to pay
for the work Allison performed on the Trailing Edge project.
There was sufficient evidence presented to the jury and by a preponderance of
that evidence, we find no reversible error in the jury's denial of Northrop's
counterclaim for damages.
We find that pursuant to California Civil Code, Section 3287(a), the trial court
did not commit reversible error by awarding Allison prejudgment interest.
Affirmed.
SULLIVAN, J., and RILEY, J., concur.