FOR PUBLICATION
ATTORNEY FOR APPELLANT
: ATTORNEY FOR APPELLEES:
DANIEL M. MILLS PETER R. FOLEY
Bloomington, Indiana Foley Foley & Peden
Martinsville, Indiana
IN THE
COURT OF APPEALS OF INDIANA
ROGERS GROUP, INC., )
)
Appellant-Plaintiff, )
)
vs. ) No. 55A05-0401-CV-1
)
DIAMOND BUILDERS, LLC, )
SPINA FOOD GROUP, LLC, )
VICTOR A. SPINA and WILLIAM SPINA, )
)
Appellees-Defendants. )
APPEAL FROM THE MORGAN SUPERIOR COURT
The Honorable G. Thomas Gray, Judge
Cause No. 55D01-0208-PL-434
October 7, 2004
OPINION - FOR PUBLICATION
BAILEY, Judge
Case Summary
Appellant-Plaintiff Rogers Group, Inc. (Rogers) appeals from a judgment entered in favor of
Appellees-Defendants Diamond Builders, LLC, Spina Food Group LLC, and Victor and William Spina
(collectively Diamond). We reverse and remand.
See footnote
Issues
Rogers raises three issues, which we consolidate and restate as the following two
issues:
Whether the trial courts award of damages on Diamonds counterclaim is clearly erroneous;
and
Whether the trial court erred in failing to award attorney fees and interest
to Rogers.
Facts and Procedural History
In 2001, Diamond was in the process of constructing a new Damons restaurant
located in Martinsville, Indiana. Diamond hired Drapalik Surveying and Engineering to design
the parking lot for the restaurant, and Stafford Construction to build the sub-base
for the parking lot, which covered approximately 50,000 square feet. Diamond contracted
with Rogers to pave a parking lot for $63,045.00. The contract with
Rogers provided, in pertinent part:
It is further understood that [Rogers] shall not be responsible for any damage
or deterioration of any of its work, whether completed or in process, resulting
from any cause or causes beyond [Rogers] control, including, but not limited to
failure of sub-grade or failure or inadequacy due to the work of others,
whether or not such failure or inadequacy was or could have been known
at the time [Rogers] Work was undertaken.
App. 216. The contract also provided that payment was due within fifteen
days of completion of the work and that Diamond was liable for attorney
fees incurred due to any breach of contract. Rogers offered a one-year
warranty on the paving.
Rogers performed the paving work in July of 2001, and submitted its invoice
for payment in September of 2001. Diamond did not pay the invoice,
and on February 21, 2002, Rogers filed a complaint against Diamond to recover
the payment due. On February 25, 2002, Rogers and Diamond agreed to
suspend the litigation and allow Diamond to pay the amount owing over five
months, plus any legal fees. Diamond paid Rogers $53,000.00, but refused to
pay the final payment of $8,369.49 plus interest and attorney fees.
That spring, Diamond began complaining about the workmanship of the parking lot, noting
several areas that would puddle and drain slowly after rains, and a separate
area where a heavy vehicle rutted the asphalt surface. In July of
2002, Rogers repaired several areas by placing additional asphalt in the low spots.
Diamond was dissatisfied with the patching work and contacted Wallace Construction, another
paving contractor, to provide an estimate to repair the parking lot. Wallace
estimated repairs would cost $15,521.00, which included milling approximately 200 linear feet of
pavement and repaving and restriping the entire parking lot. On August 27,
2002, Diamond filed a counterclaim against Rogers seeking damages to repair the parking
lot.
On July 8, 2003, the trial court conducted a bench trial on Rogers
complaint and Diamonds counterclaim. The trial court entered the following conclusions of
law:
The Court finds that the plaintiffs claim for debt with interest and attorney
fees is appropriate. Neither party has directed the Court to any case
law concerning set-offs that would toll or reduce attorney fees and interest further
than the Court has already done in its findings. That the plaintiff
owes the defendant under the contract. That the plaintiff is liable to
the counter-plaintiff for defective workmanship. That the only remedy is to redo
the parking lot. The only appropriate way to do that is to
entirely mill-off and resurface the parking lot according to Wallace Constructions bid.
App. at 15.
The trial court entered judgment for Rogers in the amount of $21,217.97 on
Rogers complaint, which included $7,504.80 in attorney fees and $5,343.68 in prejudgment interest,
and entered judgment for Diamond in the amount of $15,521.00 on Diamonds counterclaim.
Diamond filed a motion to correct error, which the trial court granted,
finding that Rogers was not entitled to attorney fees and interest because Diamonds
counterclaim exceeded Rogers principal recovery under the contract. The trial court entered
a revised judgment in favor of Diamond for $7,152.00. Rogers now appeals.
Discussion and Decision
A. Standard of Review
When a party has requested specific findings of fact and conclusions of law
pursuant to Indiana Trial Rule 52(A), the reviewing court may affirm the judgment
on any legal theory supported by the findings. Mitchell v. Mitchell, 695
N.E.2d 920, 923 (Ind. 1998). In reviewing the judgment, we must determine,
first, whether the evidence supports the findings and, second, whether the findings support
the judgment. Ahuja v. Lynco Ltd. Med. Research, 675 N.E.2d 704, 707
(Ind. Ct. App. 1996), trans. denied. The judgment will be reversed
only when clearly erroneous. Id. Findings of fact are clearly erroneous
when the record lacks any evidence or reasonable inferences from the evidence to
support them. Id. To determine whether the findings or judgment are
clearly erroneous, we consider only the evidence favorable to the judgment and all
reasonable inferences flowing therefrom, and we will not reweigh the evidence or assess
witness credibility. Id. A judgment is clearly erroneous if our examination
of the record leaves us with the firm conviction that a mistake has
been made. Owensby v. Lepper, 666 N.E.2d 1251, 1256 (Ind. Ct. App.
1996), rehg denied.
B. Analysis
1. Judgment on Counterclaim
Rogers makes a twofold argument that the trial courts order was clearly erroneous.
First, Rogers contends that the trial court erred in finding in Diamonds
favor on the counterclaim. Second, Rogers argues that the trial courts conclusion
that the only remedy is to redo the parking lot was not supported
by the findings. We address each argument in turn.
Rogers asserts that all the experts agreed that the parking lot was well
built. In fact, Richard Wallace, Diamonds expert witness, testified that he does
not guarantee puddle-free parking lots on his own work, and that puddles less
than one-eighth inch deep do not need to be repaired. No evidence
in the record establishes the water depth in the photographic exhibits.
However, according to Rogers own expert witness, Jerry Barnes, there was no indication
that these depressions in the parking lot were due to sub-base failure.
This revelation dispelled Rogers contention that the depressions were due to sub-base failure
and therefore beyond its responsibility. Barnes also testified that paving contractors typically
check and adjust the grade on paving projects to insure that the pavement
drains properly. In fact, Rogers did fine grade the existing sub-base, and
paving contractors typically have an obligation to insure that a paving project has
adequate drainage even if they are not responsible for the sub-base.
Rogers did repair several areas in the parking lot in July of 2002,
by adding additional asphalt to fill in the existing depressions. Rogers used
half-inch aggregate on top of the existing asphalt. Gary Barrow, construction manager
for Rogers, admitted that he wasnt very proud of the patch job because
it detracted visually from the new parking lot. Tr. at 120.
The parking lot at Damons was visible from the nearby highway, and the
attractiveness of the outside features of the restaurant, including the parking lot, was
important to bring in business.
From our review of the record, we conclude that the evidence and the
reasonable inferences that can be drawn therefrom support the decision of the trial
court. Specifically, the trial court could have reasonably found that the depressions
repaired by Rogers exceeded a depth of one-eighth inch, and that some of
the repairs were unattractive and needed to be redone, even if they were
structurally sound.
See footnote Accordingly, the conclusion that Rogers is liable to Diamond on
its counterclaim is supported by the evidence.
However, with respect to Rogers argument that the trial court erred in finding
that the repaving the parking lot was the
only remedy, we agree with
Rogers that the evidence did not support this conclusion.
Wallace, who provided the bid to repave the parking lot, testified that repaving
the lot was not necessary. Wallace testified that as one possible remedy,
You can mill out around the area that is holding water and put
a new surface course in there to take a depression out and then
tie it all in . . . flush. Tr. at 43.
According to Wallace:
[the parking lot] can be repaired . . . uh . . .
in a fashion that it really wouldnt stick out like a patchwork job
. . . . [M]ost of the depressed areas are around the outside
edges and parking areas, except where the drain is. In my opinion
they can be milled out where the parking areas are . . .
milled out to a point to still maintain positive drainage and overlaid in
those areas.
Tr. at 55.
See footnote
This testimony indicates that repaving the entire lot was not the only option
that would remedy the puddling and prior patching. On remand, the trial
court should conduct further proceedings to determine the cost to repair only the
areas Wallace estimated needed to be milled.
2. Attorney Fees and Prejudgment Interest
Rogers also argues that the trial court erred in failing to award attorney
fees and interest pursuant to the paving contract and subsequent settlement agreement to
suspend the litigation.
Generally, Indiana follows the American Rule, which requires each party to pay his
or her own attorney fees. Willies Constr. Co. v. Baker, 596 N.E.2d
958, 963 (Ind. Ct. App. 1992), trans. denied. However, parties
may shift the obligation to pay attorney fees through contract or agreement, and
courts will enforce such agreements as long as they are not contrary to
law or public policy. Id.
A provision for payment of attorney fees is against public policy when the
opposing party successfully asserts a counterclaim resulting in a judgment exceeding the judgment
awarded to the other party. Id. When a party successfully asserts
a contract claim against another, and the contract calls for the payment of
attorney fees, an award of attorney fees should be reduced by a proportionate
amount between the recovery under the contract and the recovery on the counterclaim.
Id. (citing Burras v. Canal Constr. and Design Co., 470 N.E.2d 1362,
1370 (Ind. Ct. App. 1984)).
In Willies Construction, the Bakers owed Willies Construction approximately $13,000 for construction of
a new house. However, the Bakers claimed that Willies Construction breached the
construction contract by failing to build a basement to the depth set forth
in the contract. The trial court awarded the Bakers $24,000 in damages
caused by Willies Constructions breach of contract, but also awarded Willies Construction the
$13,000 owed on the contract, plus attorney fees and interest. This Court
reversed the trial courts award of attorney fees and interest because the Bakers
recovery on its counterclaim exceeded the amount of the contract claim.
Here, at the time Rogers filed its complaint, Diamond owed the entire $63,045.00
for the paving work. However, days after filing the complaint, Rogers and
Diamond agreed to suspend the litigation as long as Diamond made a series
of payments to Rogers in order to pay off the amount owed.
After making the first three payments, Diamond failed to pay the remainder, and
Rogers reinstituted the litigation. Thus, while at the time the trial court
entered judgment, Diamond only owed Rogers $8,369.49 in principal, Rogers had already received
post-complaint payments totaling $53,000, a key fact that distinguishes this case from Willies
Construction. Accordingly, Diamonds recovery from its counterclaim did not exceed Rogers recovery
under the contract, and the trial court erred in failing to enforce the
terms of the contract and settlement agreement.
III. Conclusion
For the foregoing reasons, the evidence does not support the trial courts finding
that the only remedy is to redo the parking lot, and thus, its
conclusion that Diamond should recover damages for repaving the entire parking lot is
clearly erroneous. Further, the trial court erred by failing to award Rogers
its attorney fees and interest. We remand to the trial court to
conduct further proceedings consistent with this opinion.
Reversed and remanded.
SHARPNACK, J., and MAY, J., concur.
Footnote:
We hereby deny Rogers request for oral argument.
Footnote: At trial, Rogers employees testified that William Spina indicated that he would
have the parking lot seal-coated, and thus did not care about the appearance
of the patching. Spina denied that Rogers offered any options on the
type of repair.
Footnote: On questioning by the trial court, Wallace indicated that he did not
have the measurements and thus, could not estimate the cost for repaving only
those areas that would be milled, which, according to his estimate, totaled 200
linear feet.