ATTORNEY FOR APPELLANT: ATTORNEYS FOR APPELLEE:
THOMAS A. PASTORE V. SAMUEL LAURIN, III
Pastore & Gooden THERESA M. RINGLE
Indianapolis, Indiana Bose McKinney & Evans LLP
Indianapolis, Indiana
IN THE
COURT OF APPEALS OF INDIANA
LISA R. BIGLEY, as a Taxpayer within the MSD )
of Wayne Township, and for All Other Similarly- )
Situated Citizens and Taxpayers, )
)
Appellant-Plaintiff, )
)
vs. ) No. 49A02-0310-CV-893
)
MSD OF WAYNE TOWNSHIP SCHOOLS, )
Acting by and through its School Board, )
)
Appellee-Defendant. )
APPEAL FROM THE MARION CIRCUIT COURT
The Honorable Theodore M. Sosin, Judge
Cause No. 49C01-0309-PL-2645
December 9, 2004
OPINION - FOR PUBLICATION
KIRSCH, Chief Judge
Lisa R. Bigley, as a taxpayer within the Metropolitan School District of Wayne
Township, and for all similarly-situated citizens and taxpayers, brings this appeal alleging that
the trial court erred when it denied her motion for a preliminary injunction
on the basis that Bigley failed to show a reasonable likelihood of success
on the merits. She argues that she has a reasonable likelihood of
success on the merits because the bidding process for the construction of a
public works project was not open to competition, the Wayne Township School Board
(Board) improperly determined that the bid of R.L. Turner Corporation (Turner) was the
lowest responsive bid, and the Board improperly determined that Turner was a responsible
bidder, all in violation of statute.
We affirm.
FACTS AND PROCEDURAL HISTORY
In 2002, the Board entered into an agreement with Schmidt and Associates (Schmidt)
to design the Lynhurst Project, a seventh and eighth grade center that included
a pool for student and community use. Schmidt was also charged with
preparing a set of plans and specifications, assisting Wayne Township in conducting a
bid letting and the award of contracts, and assisting in overseeing the construction
of the project. Geupel Demars Hagerman (GDH) was employed as the construction
manager for the project.
Schmidt employed L & W Construction Co. (L & W) as a pool
consultant for the pool portion of the Lynhurst Project (Pool Project.) L
& Ws role was to prepare plans and specifications for the Pool Project,
prepare a budget for the project, obtain necessary permits and approvals, assist with
the determination of whether equipment or supplies other than those specified were of
equal quality and status to those specified, and oversee the work of the
successful bidder on the project.
L & W prepared the specifications for the Pool Project, which included descriptions
of filters, gutters, and other equipment. L & W specified components manufactured
by Paddock Pool Equipment Company, Inc. (Paddock), but provided that bidders could request
approval for substitutions that were of equal quality to those specified.
After the specifications were made public, Turner requested approval to substitute a number
of components specified for those made by a different manufacturer. L &
W recommended the approval of all of the substitutions requested, except for a
fiberglass filter. However, it noted that the same filter made of stainless
steel would be acceptable. Ultimately, two bidders submitted bids for the Pool
Project. J.C. Ripberger Construction (J.C. Ripberger) submitted a bid that relied upon
a subcontract bid from L & W for the pool components. Similarly,
Turner submitted a bid that relied upon a subcontract bid from Spear Corporation
(Spear) to supply and install the pool system components.
On September 23, 2003, Bigley filed suit to enjoin the award of the
Pool Project on the basis that it was designed, bid, and awarded in
violation of statute. On that same date, the trial court granted Bigleys
request for a temporary restraining order. Three days later, the trial court
dissolved the temporary restraining order. On September 30, 2003, GDH recommended to
the Board that the Pool Project be awarded to Turner, which it determined
had submitted the lowest responsive bid from a responsible bidder.
On October 2 and October 8, 2003, the trial court conducted a hearing
on Bigleys complaint. Thereafter, the trial court issued findings and conclusions denying
Bigleys request for a preliminary injunction. The Board awarded the Pool Project
to Turner, and Turner began construction of the pool. Bigley now appeals.
DISCUSSION AND DECISION
Bigley argues that the trial court erred in denying her petition for a
preliminary injunction. The grant or denial of a preliminary injunction is within
the sound discretion of the trial court, and the scope of appellate review
is limited to deciding whether there has been a clear abuse of discretion.
Roberts Hair Designers, Inc. v. Pearson, 780 N.E.2d 858, 863 (Ind. Ct.
App. 2002); Daugherty v. Allen, 729 N.E.2d 228, 232 (Ind. Ct. App. 2000),
trans. dismissed; Union Twp. Sch. Corp. v. State ex rel. Joyce, 706 N.E.2d
183, 189 (Ind. Ct. App. 1998), trans. denied (1999); City of Gary v.
Stream Pollution Control Bd. of State of Ind., 422 N.E.2d 312, 315 (Ind.
Ct. App. 1981). When determining whether or not to grant a preliminary
injunction, the trial court is required to make special findings of fact and
state its conclusions thereon. Roberts Hair Designers, 780 N.E.2d at 863; Daugherty,
729 N.E.2d at 232. When findings and conclusions are made, the reviewing
court must determine if the trial courts findings support the judgment. Roberts
Hair Designers, 780 N.E.2d at 863; Daugherty, 729 N.E.2d at 232. The
trial courts judgment will be reversed only when clearly erroneous. Roberts Hair
Designers, 780 N.E.2d at 863; Daugherty, 729 N.E.2d at 232. Findings of
fact are clearly erroneous when the record lacks evidence or reasonable inferences from
the evidence to support them. Roberts Hair Designers, 780 N.E.2d at 863;
Daugherty, 729 N.E.2d at 232. A judgment is clearly erroneous when a
review of the record leaves us with a firm conviction that a mistake
has been made. Roberts Hair Designers, 780 N.E.2d at 863. We
consider the evidence only in the light most favorable to the judgment and
construe findings together liberally in favor of the judgment. Id.; Daugherty, 729
N.E.2d at 232.
The power to issue a preliminary injunction should be used sparingly, and such
relief should not be granted except in rare instances in which the law
and facts are clearly within the moving partys favor.
Roberts Hair Designers,
780 N.E.2d at 863; Daugherty, 729 N.E.2d at 233; Union Twp. Sch. Corp.,
706 N.E.2d at 189. To obtain a preliminary injunction, the moving party
has the burden of showing by a preponderance of the evidence that:
1) its remedies at law are inadequate, thus causing irreparable harm pending resolution
of the substantive action; 2) it has at least a reasonable likelihood of
success at trial by establishing a prima facie case; 3) its threatened injury
outweighs the potential harm resulting from the granting of an injunction; and 4)
the public interest would not be disserved.
See footnote
Hughes v. City of Gary,
741 N.E.2d 1168, 1175 (Ind. 2001); Dicen v. New Sesco, Inc., 806 N.E.2d
833, 841-42 (Ind. Ct. App. 2004); Roberts Hair Designers, 780 N.E.2d at 863;
Daugherty, 729 N.E.2d at 232-33; Union Twp. Sch. Corp., 706 N.E.2d at 189.
In this case, Bigley argues that the Board has not followed the statutory
procedures in receiving bids for the Pool Project. IC 36-1-12-4 specifies the
procedure for obtaining bids for public works projects that exceed the specified size.
The purpose behind competitive bidding statutes is to safeguard the public against
fraud, favoritism, graft, extravagance, improvidence, and corruption and to insure honest competition for
the best work or supplies at the lowest reasonable cost.
Schindler Elevator
Corp. v. Metro. Dev. Commn, 641 N.E.2d 653, 657 (Ind. Ct. App. 1994).
Bigley first argues that the specifications adopted by the Board precluded competition by
limiting which companies could meet the requirements. IC 36-1-12-4(b)(1) requires the Board
to prepare general plans and specifications describing the kind of public work required
and avoid specifications that might unduly limit competition. Bigley asserts that L
& W specified products that it had an exclusive franchise or right to
sell in the area. She compares the Pool Project specifications to those
in
Monaghan v. City of Indianapolis, 37 Ind. App. 280, 291-92, 76 N.E.
424, 428 (1905), where a plaintiff challenged the award of a paving project
to a bidder. There, the plaintiff complained that the paving product specified
was a patented process. Because the patentee had absolute control over the
price at which it would supply the paving, the plaintiff argued that the
competitive bidding process was undermined. We agreed, and explained that if a party
holds the exclusive right to use and to sell a patented process, the
choice of the patented improvement amounts practically to a choice of the contractor.
We concluded that so long as the patentee may sell or may
refuse to sell to anyone the right to use the article, there can
be no competition where the patentee owns and controls the process and other
potential bidders can only procure the process from the patentee. Id.
Here, the trial court concluded that the essence of Bigleys complaint was that
the project was not competitively bid, but that because both J.C. Ripberger and
Turner submitted bids, her contention was without merit. Further, it concluded that
Turner did not gain a material advantage over J.C. Ripberger in the bidding
process. These conclusions were supported by its findings that L & W,
the pool consultant on the Pool Project, prepared the pool specifications and drawings.
The trial court also found that L & W does not manufacture
its own pool equipment, but is an authorized, though not exclusive, dealer for
Paddock, which is a pool equipment supplier/manufacturer that also sells its equipment directly.
These findings were supported by the testimony of Gary Richard Smith, senior
project manager for GDH, and John Wisel, president of L & W.
Smith testified that L & W works as a pool contractor and is
a dealer for Paddock equipment. Wisel confirmed that L & W is
a dealer of Paddock equipment but explained that it had no region or
area that it controlled and that Paddock sells its equipment to others if
they request it.
The court also found that although L & W specified certain pool equipment
by manufacturer as the quality standard in the pool specifications, there was a
process for interested bidders to seek approval of substitute pool equipment. The
evidence showed that bidders and potential bidders utilized this process. Wisel testified
that L & W approved a number of substitutions, but rejected a Neptune
Benson fiberglass filter as a substitute for the filter listed in the Pool
Specifications, suggesting that the stainless steel version of the filter would be acceptable.
Whitten also received approval for its perimeter gutter system in lieu of
the gutter system in the pool specifications. Moreover, Wisel testified that a
similar process is usually established regardless of which company provides the pool specifications.
He explained that when firms other than L & W serve as
pool consultants, they do not specify Paddock pool equipment. In those cases,
Wisel testified that he submits a request to substitute Paddock equipment for the
named equipment.
The trial court found that although L & W identified various manufacturers and
suppliers of pool equipment as approved, there were ambiguities in the Pool Project
specifications with respect to whether one manufacturer/supplier was required to provide the gutter
system and pool deck equipment. These findings were supported by Wisels testimony.
He explained that because L & W, as the consultant, was responsible
for the quality of the project overall, it decided to approve one manufacturer
as a standard and then permit other manufacturers to submit a request for
approval providing documentation on what they were going to bid on.
Transcript
at 93. He testified that L & W recommended approvals of all
of the substitute equipment submitted for approval. Moreover, Wisel testified that no
company submitted any requests for clarification regarding the Pool Project specifications.
The instructions to the bidders included information on how to obtain approval for
substituting Paddock components for others of similar quality. Accordingly, there was no
requirement that the bidders use Paddock equipment. Further, even if the bidders
did elect to use Paddock equipment, they could obtain it from Paddock directly,
without the intervention of L & W. Thus, unlike in Monaghan, the
choice of the product here did not constitute a choice in the contractor.
In fact, Smith testified that Turner, the winning bidder, intended to use
Neptune Benson equipment, for which it had sought approval to substitute, instead of
Paddock equipment.
Bigley further contends that permitting L & W, the pool consultant, to submit
a bid for pool construction created an appearance of bias toward L &
W that caused potential bidders to opt not to submit a bid.
The trial court found that L & W has served as the pool
consultant on eight publicly-bid projects in Indiana. In each instance, multiple bids
were submitted, resulting in competition. It further found that Natare and Spear,
L & Ws competitors, have also served as pool consultants on other publicly
bid projects and that a group of pool contractors regularly submits bids for
pool construction public works projects in Indiana, including Acquicious, J.C. Ripberger, Turner, Natare,
and Spear. These findings were supported by Wisels testimony that of the
eight public works projects on which L & W has served as pool
consultant, it was awarded the contract five times, but the contract went to
others in the remaining cases. Wisel testified that L & W had
bid on hundreds of public works projects and that Acapulco Pools, Aquicious, Turner,
J.C. Ripberger, Natare, and Spear all bid on projects in this area.
He further testified that Spear and Natare have served as consultants on other
public works projects and that L & W bid on those projects as
well. The trial courts conclusions on this issue were not clearly erroneous.
Bigley next argues that Turners winning bid was unresponsive because it contained material
variations from the Pool Project specifications. Competitive bidding procedures require the Board
to award the contract to the lowest responsible and responsive bidder or reject
all bids submitted.
Koester Contracting, Inc. v. Bd. of Commrs of Warrick
County, 619 N.E.2d 587, 589 (Ind. Ct. App. 1993); Irwin R. Evens &
Son, Inc. v. Bd. of Indianapolis Airport Auth., 584 N.E.2d 576, 585 (Ind.
Ct. App. 1992). This requirement sets a minimum threshold for responsiveness; it
does not require, or authorize, a search for the most responsive bidder.
Schindler Elevator Corp., 641 N.E.2d at 658. IC 36-1-12-4(b)(8) and (10) provide:
(8) Except as provided in subsection (c), the board shall:
(A) award the contract for public work or improvements to the lowest responsible
and responsive bidder; or
(B) reject all bids submitted.
(10) In determining whether a bidder is responsive, the board may consider the
following factors:
(A) Whether the bidder has submitted a bid or quote that conforms in
all material respects to the specifications.
(B) Whether the bidder has submitted a bid that complies specifically with the
invitation to bid and the instructions to bidders.
(C) Whether the bidder has complied with all applicable statutes, ordinances, resolutions, or
rules pertaining to the award of a public contract.
A bid is deemed responsive if it conforms in all material respects to
the awarding authoritys specifications.
Schindler Elevator Corp., 641 N.E.2d at 657; Irwin
R. Evens & Son, 584 N.E.2d at 585. Specifications are descriptions of
the physical characteristics, functional characteristics, extent, or nature of a public work project.
Irwin R. Evens & Son, 584 N.E.2d at 585. While minor
variances will not render a bid invalid, a material variance which affords one
bidder a substantial advantage not available to other bidders destroys the competitive character
of the bidding process and must be rejected by the awarding body as
unresponsive. Schindler Elevator Corp., 641 N.E.2d at 657; Irwin R. Evens &
Son, 584 N.E.2d at 585.
Specifically, Bigley cites as unresponsisve Turners bid details that it intended
to use a Neptune Benson filter system and an inferior grade of guttering
system. The trial court found that there was a legitimate basis for
the Board to award the contract to Turner. Although the Instructions to
Bidders specified that any material omission or discrepancy in a bidders bid would
render the bid non-responsive and subject to rejection, it further provided that the
Board had the right to waive minor discrepancies, omissions, variances, or irregularities.
The trial court found that Neptune-Benson submitted a request to Schmidt through L
& W for approval to substitute its filtration equipment, perimeter gutter system, steel
hair and lint strainers, pumps, and valves for those enumerated in the pool
specifications. L & W and Schmidt recommended the approval of all of
the components except the fiberglass filter submitted for approval and noted that a
stainless steel model of the filter could be an acceptable substitution. These
findings were supported by the testimony of Wisel and Smith.
Also, Bigley notes the specifications requirement that all of the equipment and components
for the Pool Project was to be supplied and manufactured by a single
manufacturer. The Pool Project specifications are outlined in Sections 13150 to 13155
of the Project Manual. The specifications provide:
All work called for in Section 13150, Section 13152 and, Section 13154 shall
be, and remain through the warranty periods, the sole responsibility of a single
contractor specializing in the construction of swimming pools and the installation of swimming
pool equipment.
Appellants Appendix at 156. The trial court found that this requirement was
intended to provide a single source of responsibility, but did not require that
the prime contractor be able to complete all of the requirements by its
own forces without the use of a swimming pool contractor. The trial
court found that Turners bid revealed that it would provide the concrete through
its own forces and all pool equipment and accessories through its subcontractor, Spear.
Similarly, J.C. Ripbergers bid proposed using L & W as a subcontractor
for all pool equipment and accessories. These findings were supported by the
evidence, including Wisels testimony that L & W required one single pool contractor
because [a] swimming pools a complicated building construction component and it[]s best to
have one person responsible for the complete construction. Transcript at 96.
However, he testified that there was no prohibition on the single pool contractor
being a subcontractor to the general contractor and no requirement that the entity
that installed the pool and equipment also oversee the construction unrelated to the
pool and equipment. He explained that the specifications were not drafted with
the intention of having a single manufacturer of pool equipment provide each category
of equipment, and it was acceptable if more than one pool manufacturer provided
the pool equipment.
Finally, Bigley contends that the Board failed to determine whether Turner was a
responsible bidder before awarding it the contract for the Pool Project. IC
36-1-12-4(b)(11) requires the Board to determine whether a bidder is a responsible bidder.
In doing so, the Board may consider the ability and capacity of
the bidder to perform the work, the integrity, character, and reputation of the
bidder, and the competence and experience of the bidder.
Where a board is vested with discretionary power to enter into public contracts
pursuant to competitive bidding, such as determining the best or most responsible bidder
as well as the lowest bid, an honest exercise of such discretion will
not be disturbed by the courts. Irwin R. Evens & Son, 584
N.E.2d at 585. Smith testified that he reviewed the bids and determined
whether they were responsible and responsive. He determined which bid was the
apparent low bid and reviewed the bids to determine whether they were technically
correct, whether the bid complied with the invitation to bid and the instructions
to bidders, whether the bidder complied with all of the applicable laws and
rules, and whether the bidder had any historical problems. He testified that
a responsible bidder is one which can provide a sufficient bond and for
which there is no known history of problems. He explained that a
consideration of a bidders ability and capacity to perform the work, its reputation,
its competence, and its experience are part of the responsible bidder determination and
that he determined that Turner met these qualifications.
We conclude that the trial courts conclusions are supported by its findings and
that its findings are supported by the evidence. The trial court did
not err in determining that Bigley failed to show a reasonable likelihood of
success on the merits and therefore in denying Bigleys motion for a preliminary
injunction.
Affirmed.
BAKER, J., and ROBB, J., concur.
Footnote:
Bigley cites City of Gary, 422 N.E.2d at 315, for the proposition
that
she need not prove either irreparable injury nor a balance of hardship
in favor of the taxpayers because the legislature has statutorily declared that the
acts sought to be enjoined are unlawful or clearly against the public interest.
However, were we to interpret this exception as Bigley does, this lower
standard of review would apply any time a plaintiff alleged a violation of
statute and the exception would eclipse the rule. Moreover, in Union Ins.
Co. v. State ex rel. Indiana Dept of Ins., 401 N.E.2d 1372, 1375
(Ind. Ct. App. 1980), a case relied upon by the City of Gary
court, a statute specifically conferred a right on the State to seek an
injunction in specified instances. This is not the case here. Nonetheless,
we need not resolve this question, as we decide this case on the
likelihood of success on the merits factor, which both parties agree Bigley must
prove here.